PEPPERMILL BRT

Status: Archived Projects

PROJECT DETAILS
RTC Project No. 0611001

RTC Project Manager (PM)
Ian Chamberlain

RTC Public Transportation and Operations Department
(775) 348-0400

Design Firm: Kimley-Horn and Associates

Construction Contractor:  Q and D Construction

PROJECT DESCRIPTION
The project is at Virginia Line RAPID station at Peppermill northbound.

LATEST NEWS
The project reached substantial completion and the bus stop is operational.

SCHEDULE
Planning: 2020
Environmental: 2020
Preliminary Design: 2021
Final Design: 2022
Construction: 2023

FINANCIAL INFORMATION
Total Project Estimate: $3,246,000
Funding Source: RTC Fuel Tax


Post updated on:  October 31, 2023

Peppermill BRT Project Map