Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 0711001
RTC Project Manager (PM)
Bryan Byrne, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Jacobs Engineering Group, Inc.
Construction Contractor: To be determined
PROJECT DESCRIPTION
The project includes removal and replacement of existing bridge that was constructed in 1937.
LATEST NEWS
The design team is currently developing a workshop to gather public input on specific aesthetic features for the bridge. This workshop will be open to the public from August 5, 2024, to September 27, 2024. Please visit the projects website for more information at www.sierrastreetbridge.com.
SCHEDULE
Planning: N/A
Environmental: Fall 2024 – Fall 2025
Preliminary Design: May 2023 – May 2024
Final Design: June 2024 – May 2026
Construction: To be determined
FINANCIAL INFORMATION
Total Project Estimate: $33,822,128
Funding Source: Federal
- Bridge Formula Program Off-System – $3.5M (PE) and $12.5M (CON)
- Surface Transportation Block Grant (STBG) Bridge – $10.8M (CON)
Post updated on: September 27, 2024
Sierra Street Bridge Replacement Project Map