Status: Active Projects
PROJECT DETAILS
RTC Project No. 0222030
RTC Project Manager (PM)
Kimberly Diegle, P.E.
(775) 335-1884
kdiegle@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: Eastern Sierra Engineering
Construction Contractor: Q & D Construction
PROJECT DESCRIPTION
This project will rehabilitate the pavement on Stanford Way from Greg Street to Glendale Avenue. Other improvements will include new sidewalk on the west side of Stanford Way, curb and gutter and driveway replacements, drainage upgrades, and upgrades for ADA accessibility.
LATEST NEWS
Q and D Construction was awarded the construction contract. Construction began in early March and will continue for approximately three months. Stanford Way is open to southbound traffic only. Detours are provided and business access will remain open. Parking on Stanford Way is not be allowed during construction. Please see the Weekly Traffic Control Report updates for further information.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Fall 2022 to Spring 2023
Final Design: Spring 2023 to Fall 2023
Construction: March 2024 to May 2024
FINANCIAL INFORMATION
Total Project Estimate: $2,916,707
Funding Source: RTC Fuel Tax
Post updated on: April 29, 2024