SUN VALLEY BOULEVARD CORRIDOR IMPROVEMENTS – PHASE 2

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 0221002

RTC Project Manager (PM)
Jessica Dover,P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: Nichols Consulting Engineers (NCE)

Construction Contractor: To be determined

PROJECT DESCRIPTION
Sun Valley Boulevard Corridor Improvements:

  • Scottsdale Road to 7th Avenue

LATEST NEWS
NCE is continuing preliminary design efforts and ; thirty percent design is anticipated in Spring 2025.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Summer 2025
Final Design: Spring 2026
Construction: Summer 2027

FINANCIAL INFORMATION
Total Project Estimate:
 28,400,000
Funding Source: RTC Fuel Tax

Post updated on: March 27, 2025