Status: Active Projects
PROJECT DETAILS
RTC Project No. 0247012
RTC Project Manager (PM)
Ashley Hurlbut, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Kimley-Horn and Associates
Construction Contractor: Sierra Nevada Construction, Inc.
PROJECT DESCRIPTION
The project is part of RTC’s Traffic Engineering Program and includes analysis and improvements to spot locations regionwide:
- (Reno) North McCarran Boulevard and 7th Street – Evaluate traffic, bus, and pedestrian circulation and safety improvements near the intersection of McCarran Boulevard and 7th Street.
- (Reno) South Virginia Street and Center Street – Pedestrian safety improvements at the roundabout.
- (Reno) Vassar Street and Harvard Way – Modify intersection pavement markings to improve northbound to westbound turning movements for RTC buses.
- (Sparks) Rock Boulevard and C Street – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
- (Sparks) North McCarran Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
- (Sparks) Rock Boulevard and York Way – Replace traffic signal controller cabinet and install new uninterrupted power source (UPS).
- (Sparks) Proctor R. Hug High School Circulation Study – Review pedestrian and circulation issues surrounding the high school for short and long term improvements.
- (Sparks) Outlets at Legends / Lincoln Way Circulation Study – Review traffic circulation and conflicts along Lincoln Way within the Outlets at Legends development.
LATEST NEWS
Construction of the project was substantially completed September 2025.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Winter 2024
Final Design: Spring/Summer 2024
Construction: Summer 2025
FINANCIAL INFORMATION
Total Project Estimate:Â $3,243, 976
Funding Source:Â RTC Fuel Tax
Post updated on: September 30, 2025