Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 245011
RTC Project Manager (PM)
Alex Wolfson, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: To be determined
PROJECT DESCRIPTION
This project will make the following improvements:
North McCarran Boulevard / York Way:
- Efficiency improvements on the east and west approaches
- Improve signal head visibility on McCarran southbound
Rock Boulevard / Greg Street
- Convert southbound left turn to improve safety
Rock Boulevard / Commerce Street
- Upgrade existing pedestrian crossing system to rapid rectangular flashing beacons (RRFBs)
Galleria Parkway / Costa Azul Drive
- Improve signal head visibility on Galleria southbound
California Avenue / Plumas Street
- Install dedicated left turn signals for all four intersection approaches
Kietzke Lane / Neil Road
- Install RRFBs at the roundabout crosswalks
South McCarran Boulevard / Caughlin Parkway / Cashill Boulevard
- Install active advanced warning system for McCarran Boulevard southbound due to limited sight distance
LATEST NEWS
The project design has reached fifty percent milestone.
SCHEDULE
Planning: Fall 2024
Environmental: N/A
Preliminary Design: Winter 2024 – Spring 2025
Final Design: Summer 2025 – Winter 2025
Construction: Spring 2026
FINANCIAL INFORMATION
Total Project Estimate: $1,731,730
Funding Source: RTC Fuel Tax
Post updated on: April 28, 2025
Traffic Signal Modifications 26-01 (Various Roads) Project Map