Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 0227005
RTC Project Manager (PM)
Garrett Rodgers, P.E.
(775)332-2139
grodgers@rtcwashoe.com
RTC Engineering Department
(775) 348-0171
Design Firm: Atkins North America
Construction Contractor: To be determined
PROJECT DESCRIPTION
Installation of Traffic Fiber Network on:
- Prater Way from Sparks Boulevard to Vista Boulevard
- Vista Boulevard from Prater Way to Kleppe Lane
LATEST NEWS
Design of project started in July 2023. Preliminary fifty percent design submittal review is complete. Preliminary ninety percent design submittal is in progress. Performing Preliminary field investigations of existing infrastructure.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: December 2023
Final Design: May 2024
Construction: Summer 2024
FINANCIAL INFORMATION
Total Project Estimate: $2,000,000
Funding Source: RTC Fuel Tax
Post updated on: April 23, 2024