VISTA BOULEVARD/PRATER WAY ITS

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 0227005

RTC Project Manager (PM)
Garrett Rodgers, P.E.
(775)332-2139
grodgers@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: Atkins North America

Construction Contractor: To be determined

PROJECT DESCRIPTION
Installation of Traffic Fiber Network on:

  • Prater Way from Sparks Boulevard to Vista Boulevard
  • Vista Boulevard from Prater Way to Kleppe Lane

LATEST NEWS
Design of project started in July 2023. Preliminary fifty percent design submittal review is complete. Preliminary ninety percent design submittal is in progress. Performing Preliminary field investigations of existing infrastructure.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: December 2023
Final Design: May 2024
Construction: Summer 2024

FINANCIAL INFORMATION
Total Project Estimate:
 $2,000,000
Funding Source: RTC Fuel Tax


Post updated on: April 23, 2024