WEDEKIND ROAD PEDESTRIAN IMPROVEMENTS

Project Overview

Label Value
Status Upcoming Projects
Project Details 245012
RTC Project Manager (PM) Ashley Hurlbut, P.E.
RTC Engineering Department (775) 335-1861
Design Firm Ashley Hurlbut
Construction Contractor To be determined

Project Description

Wedekind Road pedestrian and safety improvements. The planned installation of sidewalks along north side of Wedekind Road from Lund Lane to Sullivan Lane will improve safety for pedestrians and cyclists. The project scope also includes preventive maintenance of the pavement within the project limits.

Latest News

Sixty percent design is underway. Construction is anticipated for Summer 2027.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Winter 2025
Final Design: Winter 2026
Construction: Summer 2027

Financial Information

Total Project Estimate: $3,075,790
Funding Source: RTC Fuel Tax

To bid, click here:  https://rtcwashoe.procureware.com/login 

Project Map