Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 0713001
RTC Project Manager (PM)
Scott Gibson, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: To be determined
PROJECT DESCRIPTION
The focus of this project is to provide safety improvements to Fourth Street between McCarran Boulevard and Keystone Avenue. Improvements include roundabouts at Stoker Avenue and Summit Ridge Drive, lane reductions, a multi-use path and pavement rehabilitation.
LATEST NEWS
The project is out to bid opening on December 4, 2025. The project is expected to go to construction in Spring of 2026.
SCHEDULE
Planning: N/A
Environmental: November 17 2023
Preliminary Design: May 17, 2024
Final Design: July 26, 2024
Construction: February 15, 2026
FINANCIAL INFORMATION
Total Project Estimate: $28,345,000
Funding Source: Highway Safety Improvement Program (HSIP)
Post updated on: October 28, 2025
West Fourth Street Safety Project Map