WHITE FIR REHABILITATION

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 212084

RTC Project Manager (PM)
Austin McCoy, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: DOWL Engineering

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project will rehabilitate the pavement on White Fir Street from the east bridge abutment to Woodland Avenue and Woodland Avenue to culdesac.

LATEST NEWS
The RTC and the consultant, DOWL, has begun preliminary design. Construction is scheduled for Summer 2026.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: November 2024 – March 2025
Final Design: March 2025 – October 2025
Construction: Summer 2026

FINANCIAL INFORMATION
Total Project Estimate: $4,145,667.00
Funding Source: RTC Fuel Tax

Post updated on: February 25, 2025