PROJECT DETAILS
RTC Project No. 0214001
RTC Project Manager (PM)
Scott Gibson, P.E.
(775) 335-1874
RTC Engineering Department
(775) 348-0171
Design Firm: HDR Inc.
Construction Contractor: To be determined
PROJECT DESCRIPTION
This project is to resurface three bridges in the City of Reno: Second Street, Vine Street and Keystone Avenue.
LATEST NEWS
Work on the Keystone Avenue Bridge has begun and is on schedule to be completed during WCSD fall break, October 2-8, 2023. Work on the Second Street and Vine Street bridges is not yet scheduled.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: June 16, 2023
Final Design: July 30, 2023
Construction: October 9, 2023
FINANCIAL INFORMATION
Total Project Estimate: $1, 350, 000
Funding Source: RTC Fuel Tax
Post updated on: September 29, 2023