4th Street and Woodland Avenue Roundabout

PROJECT DETAILS
RTC Project No. 0532015

RTC Project Manager (PM)
Garrett Rodgers
(775) 332-2139
grodgers@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: Kimley-Horn & Associates

Construction Contractor: Sierra Nevada Construction

PROJECT DESCRIPTION
This project includes:
Package A: New roundabout at intersection of 4th Street/Woodland Avenue along with geometric changes to 4th Street at Mesa Park Road.
Package B: Extend southbound left turn at the intersection of South Virginia Street and Kietzke Lane.

LATEST NEWS
SNC completed construction of the westbound travel lanes and northern portion of the roundabout in July 2023. Construction of the eastbound lanes and southern portion of the roundabout was completed September 2023.  Mesa Park Road is officially open in both directions. Intermittent traffic control will be implemented the last week of September to install permanent striping and signs.

The project is located in the City of Reno. 4th Street is a Nevada Department of Transportation (NDOT) maintained roadway.

The project is anticipated to be complete by fall 2023.

SCHEDULE
Planning: Complete
Environmental: N/A
Preliminary Design: Winter 2021
Final Design: February 2022
Construction: Fall 2023

FINANCIAL INFORMATION
Total Project Estimate:
 $ 5,279,124
Funding Source: Regional Road Impact Fee (RRIF)
Post updated on: September 29, 2023

4th Street and Woodland Avenue Roundabout Project Map