PROJECT DETAILS
RTC Project No. 0221002
RTC Project Manager (PM)
Jessica Dover
(775) 335-1831
RTC Engineering Department
(775) 348-0171
Design Firm: To be determined
Construction Contractor: To be determined
PROJECT DESCRIPTION
Sun Valley Boulevard Corridor Improvements:
- Scottsdale Road to 7th Avenue
LATEST NEWS
RTC is currently negotiating scope/fee with a consultant to commence preliminary design efforts for the project. A contract for engineering services is anticipated on the Fall 2023 RTC Board meeting agenda.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Summer/Fall 2025
Final Design: Spring 2026
Construction: Summer/Fall 2026
FINANCIAL INFORMATION
Total Project Estimate: 28,400,000
Funding Source: RTC Fuel Tax
Post updated on: September 29, 2023
Sun Valley Boulevard Corridor Improvements – Phase 2 Map