This project will make  the following safety and operational improvements:

Moana Lane and Baker Lane – new traffic signal


Prater Way at Fourth Street in Sparks – traffic signal upgrades.


Sparks Boulevard at Mesa Meadows Drive –  crosswalk and intersection improvements.


An Intersection Control Evaluation at the Red Rock Road/US 395/ North Virginia Street Interchange.

LATEST NEWS


Construction contract will be open for bidding. Bidding will close on October 12th.

SCHEDULE


Planning: N/A


Environmental: N/A


Preliminary Design: August 2022 to November 2022


Final Design: November 2022 to Summer 2023


Construction: Summer 2023 – Spring 2024

FINANCIAL INFORMATION


Total Project Estimate:
 $2,210,742


Funding Source: RTC Fuel Tax


Post updated on: September 29, 2023