West Fourth Street Safety

PROJECT DETAILS


RTC Project No. 0713001

RTC Project Manager (PM)


Scott Gibson, P.E.


(775) 335-1874


sgibson@rtcwashoe.com

RTC Engineering Department


(775) 348-0171

Design Firm: Wood Rodgers

Construction Contractor: To be determined

PROJECT DESCRIPTION


The focus of this project is to provide safety improvements to Fourth Street between McCarran Boulevard and Keystone Avenue. Improvements include roundabouts at Stoker Avenue and Summit Ridge Drive, lane reductions, a multi-use path and pavement rehabilitation.

LATEST NEWS


Design process is underway and RTC is working with NDOT on an environmental review.

SCHEDULE


Planning: N/A


Environmental: November 17, 2023


Preliminary Design: May 17, 2024


Final Design: July 26, 2024


Construction: February 15, 2025

FINANCIAL INFORMATION


Total Project Estimate:
 $26,585,000


Funding Source: Highway Safety Improvement Program (HSIP)

Post updated on: September 29, 2023