2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Utility Adjustment
STREET | FROM | TO | DATE |
Vista Boulevard | Brierley Way | Wingfield Parkway | 11/4-11/6 |
Kleppe Lane | E Greg Street | E Greg Street | 11/5-11/6 |
South Meadows Parkway | Double Diamond Parkway | Veterans Parkway | 11/6 |
Double R Boulevard | Amston Road | Longley Lane | 11/6 |
Ralston Street | Second Street | Fifth Street | 11/7 |
Woodland Avenue | Sugar Pine Court | Fourth Street | 11/7 |
Pavement Marking
STREET | FROM | TO | DATE |
Woodland Avenue | Sugar Pine Court | Fourth Street | 11/2 |
Double R Boulevard | Amston Road | Longley Lane | 11/2 |
South Meadows Parkway | Double Diamond Parkway | Veterans Parkway | 11/2 |
Crack Sealing
STREET | FROM | TO | DATE |
Idlewild Drive | Riviera Street | Booth Street | 11/4-11/8 |
Arlington Avenue | Skyline Boulevard | Truckee River Bridge Deck | 11/4-11/8 |
Plumas Street | Ridgeview Drive | Plumb Lane | 11/4-11/8 |
Lakeside Drive | Moana Lane | Brinkby Avenue | 11/4-11/8 |
Tanberg Drive | Seventh Avenue | Mineral Avenue | 11/4-11/8 |
Wedekind Road | Round-a-bout at Clear Acre Lane | Round-a-bout at Clear Acre Lane | 11/4-11/8 |
Wedekind Road | Lund Lane | Sparks City Limits | 11/4-11/8 |
El Rancho Drive | Wedekind Road | McCarran Boulevard | 11/4-11/8 |
Greenbrae Drive | Orovada Street | El Rancho Drive | 11/4-11/8 |
Orovada Street | City Limits | Greenbrae Drive | 11/4-11/8 |
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
November 4 – November 8
- SNC will continue to be in Phase 3-manhole raising, and sign installation.
- Stripping activities will continue.
- Localized traffic controls will be in place.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
- Starting November 4 (between US 395 and Sutro Street in Reno):
- Lane closures for privacy wall rework.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Week of November 4:
- Crews are expected to perform landscape work during the day.
- Raising utilities and miscellaneous asphalt and sidewalk concrete work.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.
November 4 – November 8
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Damonte Ranch Parkway and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
- Southbound Veterans Parkway will be reduced to a continuous single lane closure between Carat Avenue and the intersection of Steamboat Parkway/Veterans Parkway for the next few weeks.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is substantially complete.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
November 4 – November 8
- Crews will be performing major milling and paving operations at the intersection of El Rancho Drive & G Street.
- G Street to the west of the intersection will be CLOSED to all traffic within 150 feet of the intersection from 7:00 a.m. Monday, November 4 through 5:00 p.m. Friday, November 8.
- Through two-way traffic will be maintained on El Rancho Drive, lanes will be reduced, and drivers may want to use alternate routes.
- All business and residential access will remain open.
- Detour signs will be in place to direct travelers around the G Street closure.