2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Utility Adjustment
STREET | FROM | TO | DATE |
Huffaker Lane | Del Monte Lane | S Virginia Street | 10/08 |
Lakeside Drive | Evans Creek Road | Moana Lane | 10/08 |
Mount Rose Street | Arlington Avenue | S Virginia Street | 10/09 |
Holcomb Avenue | S Virginia Street | Mill Street | 10/09 |
Ralston Street | Second Street | Fifth Street | 10/09 |
Evans Avenue | Second Street | Jodi Drive | 10/09 |
Summit Ridge Drive | Summit Ridge Court | McCarran Boulevard | 10/10 |
Avenida de Landa | Sharlands Avenue | Robb Drive | 10/10 |
Timber Way | Valley Road | Sutro Street | 10/10 |
Asti Lane | Bennie Lane | Ferrari McLeod Boulevard | 10/11 |
Stead Boulevard | Silver Lake Road | Echo Avenue | 10/11 |
Bravo Avenue | Mount McClellan Street | Albert Way | 10/11 |
Punch List
STREET | FROM | TO | DATE |
Vista Boulevard | Brierley Way | Wingfield Hills Drive | 10/10 |
Sullivan Lane | Prater Way | El Rancho Boulevard | 10/10 |
Parr Circle | Parr Boulevard | Parr Boulevard | 10/10 |
Tampa Street | Timber Way | Timber Way | 10/10 |
Dickerson Road | Second Street | Second Street | 10/10 |
Holcomb Avenue | Virginia Street | Mill Street | 10/10 |
Gentry Way | Terminal Way | Chris Lane | 10/10 |
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
October 7 – October 11
- SNC will continue to be in Phase 3-manhole raising, and sign installation.
- Localized traffic controls will be in place.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Crews are expected to continue working during the night until October 11, removing/replacing concrete (curb/gutter/ped ramps/driveways) and installing conduit, pull boxes, poles, etc. at the intersection of Patriot/S Virginia.
- Northbound lane paving – Week of October 7 during the night.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, roadway striping, and landscaping.
October 7 – October 11
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
October 7 – October 11
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
- Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
- Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
No work will take place this week.
Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.