October 4, 2024

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Utility Adjustment

STREETFROMTODATE
Huffaker Lane Del Monte LaneS Virginia Street10/08
Lakeside DriveEvans Creek RoadMoana Lane10/08
Mount Rose StreetArlington AvenueS Virginia Street10/09
Holcomb AvenueS Virginia StreetMill Street10/09
Ralston StreetSecond StreetFifth Street10/09
Evans AvenueSecond StreetJodi Drive10/09
Summit Ridge DriveSummit Ridge CourtMcCarran Boulevard10/10
Avenida de LandaSharlands AvenueRobb Drive10/10
Timber WayValley RoadSutro Street10/10
Asti LaneBennie LaneFerrari McLeod Boulevard10/11
Stead BoulevardSilver Lake RoadEcho Avenue10/11
Bravo AvenueMount McClellan StreetAlbert Way10/11

Punch List

STREETFROMTODATE
Vista BoulevardBrierley WayWingfield Hills Drive10/10
Sullivan Lane Prater Way El Rancho Boulevard10/10
Parr Circle Parr Boulevard Parr Boulevard10/10
Tampa StreetTimber Way Timber Way10/10
Dickerson RoadSecond StreetSecond Street10/10
Holcomb AvenueVirginia StreetMill Street10/10
Gentry WayTerminal Way Chris Lane10/10


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

October 7 – October 11

  • SNC will continue to be in Phase 3-manhole raising, and sign installation.
  • Localized traffic controls will be in place.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Crews are expected to continue working during the night until October 11, removing/replacing concrete (curb/gutter/ped ramps/driveways) and installing conduit, pull boxes, poles, etc. at the intersection of Patriot/S Virginia.
  • Northbound lane paving – Week of October 7 during the night.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, roadway striping, and landscaping.

October 7 – October 11

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.

October 7 – October 11

  • Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
  • Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
  • Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

No work will take place this week.

Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.