September 27, 2024

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Vehicle Detection Loops 7:00 p.m. – 7:00 a.m.

STREETFROMTODATE
South Virginia StreetGreen Acres DriveDelucchi Lane9/29
South Virginia StreetNeil RoadNeil Road9/30
South Virginia StreetMeadowood Mall CircleMeadowood Mall Circle10/01
South Virginia StreetMeadowood Mall WayMeadowood Mall Way10/02
South Virginia StreetSierra Center ParkwayMcCarran Boulevard10/03

Micro-Surfacing

STREETFROMTODATE
Evans Avenue Second Street Fourth Street10/01

Thermoplastic Installation

STREETFROMTODATE
Evans Avenue Second StreetFourth Street10/04


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

September 30 – October 4

  • SNC has completed Phase 2b of construction.
  • Westbound lanes will be open and one way traffic will continue westbound through mid-week.
  • Paving operations will be completed and Phase 3 will begin for the manhole raising.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Crews are expected to continue working during the night until October 11, removing/replacing concrete (curb/gutter/ped ramps/driveways) and installing conduit, pull boxes, poles, etc. at the intersection of Patriot/S Virginia.
  • Northbound lane paving – Week of October 7 during the night.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, roadway striping, and landscaping.

September 30 – October 4

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.

September 30 – October 4

  • Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
  • Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
  • Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street. This work will occur between the hours of 9:00 p.m. and 5:30 a.m.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

No work will take place this week.

Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.