2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Vehicle Detection Loops 7:00 p.m. – 7:00 a.m.
STREET | FROM | TO | DATE |
South Virginia Street | Green Acres Drive | Delucchi Lane | 9/29 |
South Virginia Street | Neil Road | Neil Road | 9/30 |
South Virginia Street | Meadowood Mall Circle | Meadowood Mall Circle | 10/01 |
South Virginia Street | Meadowood Mall Way | Meadowood Mall Way | 10/02 |
South Virginia Street | Sierra Center Parkway | McCarran Boulevard | 10/03 |
Micro-Surfacing
STREET | FROM | TO | DATE |
Evans Avenue | Second Street | Fourth Street | 10/01 |
Thermoplastic Installation
STREET | FROM | TO | DATE |
Evans Avenue | Second Street | Fourth Street | 10/04 |
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
September 30 – October 4
- SNC has completed Phase 2b of construction.
- Westbound lanes will be open and one way traffic will continue westbound through mid-week.
- Paving operations will be completed and Phase 3 will begin for the manhole raising.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Crews are expected to continue working during the night until October 11, removing/replacing concrete (curb/gutter/ped ramps/driveways) and installing conduit, pull boxes, poles, etc. at the intersection of Patriot/S Virginia.
- Northbound lane paving – Week of October 7 during the night.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, roadway striping, and landscaping.
September 30 – October 4
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
September 30 – October 4
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
- Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
- Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street. This work will occur between the hours of 9:00 p.m. and 5:30 a.m.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
No work will take place this week.
Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.