June 13, 2025

2025 PREVENTATIVE MAINTENANCE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Pavement Patching

STREET FROMTODATE
Lakeside DriveHuffaker LanePark Gate06/09-10
Cashill BoulevardMcCarran BoulevardSkyline Boulevard06/09-10
Caughlin Parkway Alum Creek Bridge McCarran Boulevard06/10-11
Yuma Lane Hunter Lake DriveKoldewey Drive06/10-11
Beaumont Parkway Clubhouse DriveGlen Eagles Drive06/11-12
Mae Anne AvenueMesa Park RoadLasalle Heights06/12
Mesa Park RoadMae Anne Avenue Highway 4006/12
S Verdi RoadVerdi RoadBridge Street 06/12

Microsurfacing

STREETFROMTODATE
Wingfield Hills RoadRolling MeadowsVista Boulevard06/10
Shoppers Way Pyramid WayGalleria Parkway 06/11
S Wingfield Parkway Wingfield Hills RoadCart X-ing6/11
Los Altos Parkway Vista BoulevardPyramid Way06/12-13


ARLINGTON AVENUE BRIDGES PROJECT – 1ST STREET TO ISLAND AVENUE
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865

Arlington Avenue will be closed between West 1st Street and Island Avenue. Northbound traffic will be detoured to the Virginia Street bridge or Center Street. Southbound traffic and pedestrians will be detoured to the Sierra Street bridge.

  • West Street will be open to westbound traffic only between West Street and Stevenson Street.
  • Wingfield Park will remain closed from May 5, 2025, until summer 2026.
  • River recreation detours will also be in place.
  • View detour maps at ArlingtonBridges.com


MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844

Continuous single lane closures on Mill Street westbound from Greg Street/Terminal Way to the I-580 southbound ramp intersection. Daytime and nighttime construction will occur with single lane closures on Mill Street between I-580 and Terminal Way.

Bus Stop Closures:

  • The Route 12/14 eastbound bus stop at Mill Street/Matley Lane is closed
  • The Route 14 eastbound bus stop at Mill Street Gould Street is closed.

Riders should follow signage to the nearest bus stop of call RTC customer service at (775) 348-RIDE (348-7433) for real time information.

Visit MillStreetWidening.com for information and updates. Text “MillStreet” to 866-540-8466 to sign up for construction text alerts.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

June 9 – June 13

General lane restrictions in all directions to perform landscaping.


VETERANS PARWAY ITS-LONG MEADOW DRIVE TO STEAMBOAT PARKWAY
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

Intermittent single lane closures on southbound Veterans Parkway between Long Meadow Drive and Steamboat Parkway for traffic fiber installations.


TRAFFIC SIGNAL MODIFICATION 24-01
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861

June 2025

No traffic control anticipated on this project in early June.


MEADOWOOD MALL REHABILITATION
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

June 9 – June 13

Roadway work and sidewalk reconstruction to be performed on Meadowood Mall Circle between S. Virginia Street and Meadowood Mall Circle, Meadowood Mall Way between S. Virginia Street and Meadowood Mall Circle, and Neil Way between Neil Road and Meadowood Mall Circle.

Meadowood Mall Circle

  • One lane each direction will be maintained during the day.
  • Route 1 Bus Stop on Meadowood Mall Circle (at Jiffy Lube) will be temporarily closed.
  • Jiffy Lube driveway access will be maintained at all times.

Neil Way

  • One lane each direction will be maintained during the day.

Meadowood Mall Way

  • One lane each direction will be maintained during the day.


SUN VALLEY BOULEVARD CORRIDOR IMPROVEMENTS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

May 27 – June 20

Field exploration to obtain geotechnical borings for the design phase of the Project will occur on Sun Valley Boulevard from Scottsdale Road to 7th Avenue. Work will start at the north end of the project and progress to the south.

Southbound

  • One lane each direction will be maintained
  • Lane and shoulder closures anticipated
  • Nightwork to occur, approximately 7:00 p.m. – 5:00 a.m.

Northbound

  • One lane each direction will be maintained
  • Lane and shoulder closures anticipated
  • Nightwork to occur, approximately 9:00 p.m. – 11:00 a.m.

VISTA PRATER SIGNAL FIBER CONNECTION PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Installation of traffic fiber network on Prater Way from Sparks Boulevard to Vista Boulevard and Vista Boulevard from Prater Way to Kleppe Lane.

June 9 – June 13

Prater Way

  • Shoulder closures eastbound and westbound directions.
  • Intermittent lane restrictions and lane reductions through intersections.

Vista Boulevard

  • Shoulder closures northbound and southbound directions.
  • Intermittent lane restrictions and lane reductions through intersections.