October 11, 2024

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Utility Adjustment

STREETFROMTODATE
Summit Ridge DriveSummit Ridge CourtW 4th Street10/14
Summit Ridge InterchangeSummit RidgeRight of Way Fence10/14
Avenida de LandaSharlands AvenueRobb Drive10/14
Timber WayValley RoadSutro Street10/14
Asti LaneBennie LaneFerrari McLeod Boulevard10/15
Stead Boulevard Silver Lake RoadEcho Avenue10/15
Bravo Avenue Mount McClellan StreetAlbert Way10/15
Ralston StreetSecond StreetFifth Street10/16
Wingfield ParkwayVista BoulevardWingfield Springs Road10/16-18
Vista Boulevard Brierley WayWingfield Hills10/16-18

Pavement Markings

STREETFROMTODATE
Woodland AvenueSugar Pine CourtS 4th Street 10/17


SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)

RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

October 14 – October 18

  • SNC will continue to be in Phase 3-manhole raising, and sign installation.
  • Localized traffic controls will be in place.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

  • Project is substantially completed.
  • Intermittent lane shifts for punch item list work and landscape work.


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m. (day work).
  • At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
  • Week of October 14:
    • Crews are expected to continue working during the nighttime, installing concrete median, paving median island and removing concrete on Longley Lane and Huffaker Lane.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. This week crews will be performing concrete work, storm drain installation, and landscaping. Crews will begin full depth reconstruction of southbound Veterans Parkway between RC Willey and the intersection of Steamboat Parkway/Veterans Parkway. Through traffic is advised to use an alternate route, if possible.

October 14 – October 18

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.
  • Southbound Veterans Parkway will be reduced to a continuous single lane closure between RC Willey and approximately 150 feet north of the intersection of Steamboat Parkway/Veterans Parkway.


KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.

October 14 – October 18

  • Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
  • Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
  • Lane reductions and traffic shifts through the intersection of Kietzke Lane and 2nd Street.


RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
  • Limited on-street parking.


TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

No work will take place this week.

Pedestrian traffic control will remain in place on the southwest corner of El Rancho Drive and G Street.