2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Street Striping 7:00pm – 7:00am
STREET | FROM | TO | DATE |
Various Project Streets | Various | Various | 8/25 – 8/30 |
Pavement Markings 7:00am – 5:00pm
STREET | FROM | TO | DATE |
Stead Boulevard | Silver Lake Boulevard | Echo Avenue | 8/28 – 8/29 |
LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Las Brisas Boulevard between Brittania Drive and McCarran Boulevard
- Work is substantially complete.
- Contractor will be on site to complete minor work items throughout August.
- Two-way traffic anticipated to be maintained.
Los Altos Parkway between North Vista Boulevard and Goodwin Road
- Work is substantially complete.
- Contractor will be on site to complete minor work items throughout August.
- Two-way traffic anticipated to be maintained.
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
August 26 – August 30
- Crews will begin at Mae Anne and progress to Del Webb Parkway with lowering utilities in preparation of the mill and full operation to follow.
- Traffic impacts will be minimal with minor delays in specific locations with flagger control.
- This activity will last 3-4 weeks.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
- Crews working on the southbound side removing/installing new driveways, sidewalk, and pedestrian ramps.
- Night work starting the week of August 30, with closures and detours. At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day.
- West Coast Dirt Works crews will be on-site doing private development work during the weekend of August 23-26. Work to include sewer line connection along northbound lanes closer to the intersection at Patriot Boulevard.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024.
August 26 – August 30
- Two travel lanes in each direction will be maintained on Steamboat Parkway.
- Steamboat Parkway will be reduced to one lane in each direction at times.
- Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reduction at the intersection of Veterans Parkway and Steamboat Parkway.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
August 26 – August 30
- One travel lane in each direction will be maintained on E 2nd Street for shoulder work.
- A detour will be in place for eastbound traffic on E 2nd Street as crews construct trench through roudabout. Detour will be as follows:
- Road will be closed in eastbound direction at the intersection of Pringle Way and E 2nd Street.
- Eastbound traffic will be detoured back to Kietzke Lane via Manuel Street and Kuenzli Street.
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E 2nd Street and Mill Street
- Lane reductions at the intersection of E 2nd Street and Kietzke Lane for intersection work to be performed at night.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
August 26 August 30
Battle Born Way and Galletti Way
- Crews will begin work on the traffic signal system on Monday, August 20.
- Reduced lanes in eastbound direction.
- Shoulder and pedestrian access will be closed on the southeast corner of the intersection during daytime non-peak hours.
- Intermittent lane closures will occur in all directions as crew work on overhead signal systems.
- Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.
Los Altos Parkway and Galleria Parkway
- Intermittent lane closures will occur in all directions as crew work on overhead signal systems.
- Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.