2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Pavement Patching
STREET | FROM | TO | DATE |
Woodland Avenue | Sugar Pine Court | Fourth Street | 9/14 |
Micro-Surfacing
STREET | FROM | TO | DATE |
Montello Street | End of Fence | Sixth Street | 9/20 |
Ninth Street | Evans Street | Valley Road | 9/20 |
Vassar Street | Kietzke Lane | Harvard Way | 9/20-21 |
Woodland Avenue | Sugar Pine Court | Fourth Street | 9/21 |
Sugar Pine Court | Cul-de-Sac | Woodland Avenue | 9/21 |
Pavement Striping 7:00 p.m. – 7:00 a.m.
STREET | FROM | TO | DATE |
Montello Street | End of Fence | Sixth Street | 9/20 |
Ninth Street | Evans Street | Valley Road | 9/20 |
Vassar Street | Kietzke Lane | Harvard Way | 9/20-21 |
Woodland Avenue | Sugar Pine Court | Fourth Street | 9/21 |
Sugar Pine Court | Cul-de-Sac | Woodland Avenue | 9/21 |
LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Las Brisas Boulevard between Brittania Drive and McCarran Boulevard
- Work is substantially complete.
- Contractor will be on site to complete minor work items throughout August.
- Two-way traffic anticipated to be maintained.
Los Altos Parkway between North Vista Boulevard and Goodwin Road
- Work is substantially complete.
- Contractor will be on site to complete minor work items throughout August.
- Two-way traffic anticipated to be maintained.
SOMERSETT PARKWAY REHABILITATION (2024 CORRECTIVE MAINTENANCE)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
September 16 – September 20
- SNC has completed Phase 1 of construction – lowering utilities in preparation of the mill and fill operation to follow.
- There will be no activity this week.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
- Project is substantially completed.
- Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
- At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day (night work).
- Crews will be working during the night until September 27, installing concrete (curb, gutter, pedestrian ramps, and driveways) on the southbound side of South Virginia and installing electrical work ( conduit, pull boxes, poles, etc.).
- Crews will also work on the Patriot/S Virginia intersection.
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024. Intersection paving operations are scheduled for Tuesday, September 17 and Wednesday, September 18 at night between 7:00 a.m. to 7:00 p.m. During paving operations, the following traffic control restrictions will be in place. Through traffic is encouraged to use alternate routes, if possible.
September 16 – September 20
- Paving Operations: Steamboat Parkway will be reduced to a single lane in each direction between the intersection of Veterans Parkway/Steamboat Parkway and Marketplace Drive/Steamboat Parkway, September 17-18.
- Paving Operations: Eastbound Steamboat Parkway traffic will not be able to access the shopping center at Marketplace Drive. Traffic exiting the shopping center at Marketplace Drive will only be able to exit in the westbound direction. Please use Promenade Way to enter/exit the shopping center during the paving operations.
- Anticipate delays and use caution and slow speeds through the work zone.
KIETZKE INTELLIGENT TRAFFIC SYSTEMS (ITS) PROJECT
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway for Kietzke ITS Project and will continue through mid October. Project limits start at the intersection of Manual Street and E 2nd Street to the intersection of E 2nd Street to Kietzke Lane. From there, the project continues in the southbound shoulder along Kietzke Lane to Mill Street.
September 16 – September 20
- Shoulder closures and lane reductions in the southbound direction on Kietzke Lane between E. 2nd Street and Mill Street.
- Shoulder closures and lane reductions in the eastbound direction on 2nd Street between Manuel Street and Kietzke Lane.
- Lane reductions and traffic shifts through the intersection of Kietzke Lane/2nd Street. This work will occur between the hours of 9:00 p.m. and 5:30 p.m.
RALEIGH HEIGHTS REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
- Single lane closures and local traffic only on Yorkshire Drive and Carlyle Drive.
- Limited on-street parking.
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
El Rancho Boulevard & G Street
- Intermittent lane closures will occur in all directions at this location as crews work on overhead signal systems and reconstruct the right turn lane from eastbound G Street to southbound El Rancho Boulevard.
- Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.
Battle Born Way and Galletti Way
- Crews will begin work on the traffic signal system.
- In the eastbound direction, lanes will be reduced, and shoulder and pedestrian access will be closed on the southeast corner of the intersection during daytime non-peak hours.
- Intermittent lane closures will occur in all directions as crew work on overhead signal systems.
- Two-way travel will be maintained in all directions, but delays from reduced lanes should be expected during daytime non-peak hours.