2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.
Micro-Surfacing
STREET | FROM | TO | DATE |
Vista Boulevard | Brierly Way | Wingfield Hills Drive | 07/29-8/1 |
Wild Island Court | Cul-de-sac | E Lincoln Way | 8/3 |
Kleppe Lane | E Greg Street | E Greg Street | 8/3 |
Pavement Striping 7:00 p.m. – 7:00 a.m.
STREET | FROM | TO | DATE |
Vista Boulevard | Brierly Way | Wingfield Hills Drive | 07/29-8/1 |
Wild Island Court | Cul-de-sac | E Lincoln Way | 8/3-4 |
Kleppe Lane | E Greg Street | E Greg Street | 8/3-4 |
Pavement Markings (Thermoplastic)
STREET | FROM | TO | DATE |
Stead Boulevard | Silver Lake Road | Echo Avenue | 07/29-31 |
Sullivan Lane | Prater Way | El Rancho Boulevard | 07/30-8/2 |
Vista Boulevard | Brierly Way | Wingfield Hills Drive | 08/2-16 |
Vehicle Detection Loops
STREET | FROM | TO | DATE |
Vassar Street | Market Street | Kietzke Lane | 07/29 |
LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Las Brisas Boulevard between Brittania Drive and McCarran Boulevard
Work is substantially complete. Contractor will be on site to complete minor work items throughout July. Two-way traffic anticipated to be maintained.
Los Altos Parkway between North Vista Boulevard and Goodwin Road
Work is substantially complete. Contractor will be on site to complete minor work items throughout July. Two-way traffic anticipated to be maintained.
ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861
Project is substantially completed. Intermittent lane shifts for punch item list work and landscape work.
SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
- Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
- Construction during the day. Concrete work (sidewalk, curb, and gutter, driveways, etc.) along the northbound side of South Virginia.
- Night work is anticipated in August, with closures and detours. At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day.
SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861
Project is substantially completed. Intermittent lane shifts for punch item list work and landscape work.
TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Work is substantially complete at the Moana Lane/ Baker Lane, and Prater Way/ 4th Street intersections. Motorists may see occasional shoulder and lane closures for final work items.
SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
Motorists may see various lane and shoulder closures at the following locations for fiber optics installation:
- Galleria Parkway between Los Altos Parkway and Disc Drive
- Los Altos Parkway between Galleria Parkway and Ion Drive
STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction is underway and will continue through Fall 2024.
July 29 – August 2
- Two travel lanes in each direction will be maintained on Steamboat Parkway. Steamboat Parkway will be reduced to one lane in each direction at times.
- Shoulder closure for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
- Shoulder closures/lane reduction at the intersection of Veterans Parkway and Steamboat Parkway.
SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
No active traffic control for this project.
NORTH VIRGINIA UNIVERSITY REHABILITATION – LAWLOR ROUNDABOUT TO NORTH MCCARRAN BOULEVARD
RTC Project Manager, Bryan Byrne, P.E. – (775) 335–1865
July 25 to August 2
- Two-way traffic on North Virginia Street with one lane in each direction
- No on-street parking
TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 335–1897
July 29- August 2
El Rancho Drive and G Street
- Motorists should anticipate daytime shoulder and intermittent lane closures near the signalized intersection.
- At least one lane for each travel direction will remain open throughout this phase of work.
Intermittent lane and shoulder closures will occur at the following intersections between the hours of 7:00am – 5:00pm as crews complete work on traffic signal systems:
McCarran & Mayberry, Sutro & Wedekind, Golden Valley & North Hills, Arrowcreek & Wedge, Mount Rose Highway & Wedge, Sun Valley Boulevard & 5th, and Los Altos & Galleria