May 17, 2024


2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

PAVEMENT PATCHING

STREETFROMTODATE
Peckham LaneLakeside DriveBaker Lane5/20
Holcomb AvenueS Virginia StreetBurns Street5/20
Holcomb AvenueLiberty StreetRyland Street5/20
Mount Rose StreetArlington AvenueS Virginia Street5/20
Regency Way S Virginia StreetEnd Island w/Roundabout5/20
Evans Avenue Second StreetFourth Street5/20-21
Evans Avenue Freeway OverpassJodi Drive5/20-21
Liberty StreetCenter StreetHolcomb Avenue5/20-21
Ralston StreetSecond StreetFifth Street5/20-22
Stoker AvenueFourth StreetSeventh Street5/21-22
Summit Ridge DriveE Bridge AbutmentW Fourth Street5/22-23
Summit Ridge InterchangeSummit Ridge DriveS McCarran5/23-24
Summit Ridge InterchangeSummit Ridge DriveRight of Way Fence5/23-24
Avenida De LandaSharlands AvenueRobb Drive5/24
Ormand CourtGiroux StreetEnd Cul-de-sac5/24
Wingfield ParkwayVista BoulevardWingfield Springs Road5/20
Vista Boulevard Brierly WayWingfield Hills Drive5/20-24
Rock BoulevardVictorian AvenueMcCarran Boulevard5/23-24
Sullivan LanePrater WayRancho Boulevard5/23-24

CRACK SEAL

STREETFROMTODATE
Sullivan LanePrater WayEl Rancho Boulevard5/20-24
Avenida De LandaSharlands Avenue Robb Drive5/20-24
Mae Anne AvenueQuail Run RoadS McCarran5/20-24
Summit Ridge DriveSummit Ridge CourtW Fourth Street5/20-24
Summit Ridge InterchangeSummit RidgeRight of Way Fence5/20-24
Summit Ridge InterchangeSummit RidgeMcCarran Right of Way Fence5/20-24
Stoker AvenueFourth StreetSeventh Street5/20-24
Dickerson RoadW/End Second StreetSecond Street5/20-24
Grove StreetLymberry StreetWrondrel Way5/20-24
Grove StreetKietzke LaneHarvard Way5/20-24
Mount Rose StreetArlington AvenueVirginia Street5/20-24
Holcomb AvenueVirginia StreetBurns Street5/20-24
Holcomb AvenueLiberty StreetMill Street5/20-24
Liberty StreetCenter StreetHolcomb Avenue5/20-24
Evans AvenueSecond StreetFourth Street5/20-24
Evans AvenueFreeway OverpassJodi Drive5/20-24
Ninth StreetEvans AvenueValley Road5/20-24
Mt Charleston StreetStead BoulevardEcho Avenue5/20-24
Stead Boulevard Silver Lake RoadEcho Avenue5/20-24

1ST STREET REHABILITATION AND SIGNAL REPLACEMENT (VIRGINIA TO SIERRA STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Project is substantially complete but there will be some temporary traffic controls in place on occasion as the contractor addresses final cleanup and punch list items.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Expect minor lane shifts for punch item list work and landscape work.

Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):

  • Expect minor lane shifts for punch item list work and landscape work.

Phase 3 – east of US 395 Ramps to Sutro Street (Reno):

Phase 4 – Sutro Street to I-80 Ramps (Reno):

  • Expect minor lane shifts for raising utilities, final concrete and driveway work, landscaping, punch item list work, and NVE light installs.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com


SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

May 8 – May 31 (tentative dates)

  • One-way westbound-only traffic will be allowed on Selmi Drive at all times (24/7). Detours are provided for eastbound traffic thru McCarran Boulevard.

Accesses remain open for both businesses and residential.


STANFORD WAY REHABILITATION PROJECT (GREG STREET TO GLENDALE AVENUE)
RTC Project Manager, Kim Diegle, P.E. – (775) 335-1844

  • Major construction is complete and two-way traffic has been restored.
  • Shoulder and lane closures may take place intermittently as construction cleanup occuurs.
  • On-street parking may remain closed in some areas as construction wraps up.

PYRAMID WAY AND NORTH MCCARRAN BOULEVARD FIBER CONNECTIVITY
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

This project is substantially complete.  Occasional shoulder closures may occur on Pyramid Way between Nugget Avenue and C Street for final work items.


TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Moana Lane and Baker Lane/Smith Drive (Reno)

The following traffic control will be in place at the intersection of Moana Lane, Baker Lane, and Smith Drive for traffic signal installation:

  • Intermittent lane and shoulder closures.
  • Full closure of the Smith Drive approach will occur at times. A detour will be provided.
  • Full closure of the Bake Lane approach will also occur due to an adjacent project. Follow the signed detour.

Prater Way and 4th Street (Sparks)

The following traffic controls will be in place until the end of May at the intersection of Prater Way and 4th Street for traffic signal replacement:

  • A temporary all-way stop will be in effect at the intersection.
  • Various lane and shoulder closures.
  • All turning movements and driveways will remain open.

Delays are possible and motorists should consider an alternate route until the work is complete.


SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Construction is underway and will continue through June. Motorists can expect the following traffic controls:

Baring Boulevard between Sparks Boulevard and Vista Boulevard

  • Various lane and shoulder closures for fiber optic installation.
  • Lane closures (if needed) will occur Monday thru Friday, 9:00 a.m. – 3:00 p.m. daily.

Vista Boulevard between Baring boulevard and Los Altos Parkway (south)

  • Various shoulder closures for fiber optic installation.

Los Altos Parkway between Ion Drive and Sparks Boulevard

  • Various shoulder closures for fiber optic installation
  • Intermittent closure of the Table Mountain Way approach to Sparks Boulevard. A signed detour will be provided for any closures.

STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024. Traffic is shifted to the center of Steamboat Parkway between Veterans Parkway and Marketplace Drive.

May 20 to May 24 (Day Work)

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closures for westbound and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reductions at the intersection of Veterans Parkway and Steamboat Parkway.

May 22 to May 23 (Night Work)

  • The intersection of Steamboat Parkway and Veterans Parkway will be reduced to one lane in each direction with four-way stop control between the hours of 8:00 PM and 5:00 AM Wednesday night through Friday morning.
  • Stop signs and flaggers will be controlling the intersections while four Signal Poles are relocated from their existing location to their new locations.

SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closure on westbound Damonte Ranch Parkway between Promenade Way and Double R Boulevard, 7:00 a.m. to 7:00 p.m.
  • Single lane closure on eastbound South Meadows Parkway between Double R Boulevard and Veterans Parkway near I-580