Installation of Traffic Fiber Network on:

  • Prater Way from Lillard Way to Vista Boulevard.
  • Vista Boulevard from Prater Way to east bound I-80

LATEST NEWS


Design of project started in July 2023. Performing preliminary field investigations of existing infrastructure.

SCHEDULE


Planning: N/A


Environmental: N/A


Preliminary Design: Current to Summer 2023


Final Design: Fall 2023


Construction: Summer 2024

FINANCIAL INFORMATION


Total Project Estimate:
 $2,000,000


Funding Source: RTC Fuel Tax