STEAD SIGNAL IMPROVEMENTS

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 217011

RTC Project Manager (PM)
Alex Wolfson

RTC Engineering Department
(775) 348-0171

Design Firm: Kimley-Horn and Associates

Construction Contractor: To be determined

PROJECT DESCRIPTION
The project will make the following improvements along Stead Boulevard inn the North Valleys:

  • Install fiber optics between North Virginia Street and Lear Boulevard to enhance traffic signal communications and reliability
  • Left turn improvements at the Stead Boulevard / Lear Boulevard intersection to enhance safety
  • Miscellaneous traffic signal equipment upgrades to enhance aging infrastructure

LATEST NEWS
The RTC has selected Kimley-Horn and Associates to perform design services on this project. Design is now underway.

SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Fall 2024 – Spring 2025
Final Design: Summer 2025 – Fall 2025
Construction: Spring 2026

FINANCIAL INFORMATION
Total Project Estimate: $2,200,000.00
Funding Source: RTC Fuel Tax

Post updated on: November 25, 2024

Stead Signal Improvements Project Map