July 5, 2024

2024 PREVENTATIVE MAINTENANCE
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

This schedule contains weather/temperature sensitive work and may be modified if weather conditions are unfavorable.

Micro-Surfacing

STREETFROMTODATE
Summit Ridge DriveSummit Ridge CourtW Fourth Street7/8
Summit Ridge InterchangeSummit RidgeS McCarran ROW Fence7/8
Mae Anne AvenueQuail Run RoadS McCarran Boulevard7/9
Avenida de LandaSharlands AvenueRobb Drive7/10-12
Edison WayRock BoulevardMill Street7/13
Ohm PlaceMill StreetMill Street7/13

Pavement Striping 7:00 p.m. – 7:00 a.m.

STREETFROMTODATE
Summit Ridge DriveSummit Ridge CourtW Fourth Street7/8
Summit Ridge InterchangeSummit RidgeS McCarran ROW Fence7/8
Mae Anne AvenueQuail Run RoadMcCarran Boulevard7/9
Avenida de LandaSharlands AvenueRobb Drive7/10-12
Edison WayRock BoulevardMill Street7/13
Ohm PlaceMill StreetMill Street7/13

Pavement Markings (Thermoplastic)

STREETFROMTODATE
Kings RowS McCarran BoulevardKeystone Avenue7/8-12
Washington StreetFifth StreetRancho San Rafael Park7/8-12
Security CircleVirginia StreetVirginia Street7/8-12
Rock BoulevardVictorian AvenueMcCarran Boulevard7/8-9
Victorian AvenueStanford Way N McCarran Boulevard7/8
Victorian AvenuePyramid WayStanford Way7/8
Deming WayGreg StreetGlendale Avenue7/8-9
Parr CircleParr BoulevardParr Boulevard7/8-10
Ormand CourtGiroux StreetCul-de-sac7/8-10
Evans AvenueFreeway OverpassJodi Drive7/8-10
Stoker AvenueFourth StreetSeventh Street7/8-10
Timber WayValley RoadSutro Street7/8-12
Silverada BoulevardNinth StreetOddie Boulevard7/8-12
Summit Ridge DriveSummit Ridge CourtW Fourth Street7/11-12
Summit Ridge InterchangeSummit RidgeS McCarran ROW Fence7/11-12
Mae Anne AvenueQuail Run RoadS McCarran Boulevard7/12


LAS BRISAS AND LOS ALTOS RESURFACING PROJECT
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

Las Brisas Boulevard between Brittania Drive and McCarran Boulevard

Work is substantially complete. Contractor will be on site to complete minor work items throughout July. Two-way traffic anticipated to be maintained.

Los Altos Parkway between North Vista Boulevard and Goodwin Road

Work is substantially complete. Contractor will be on site to complete minor work items throughout July. Two-way traffic anticipated to be maintained.


1ST STREET REHABILITATION AND SIGNAL REPLACEMENT (VIRGINIA TO SIERRA STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

Project is substantially complete but there will be some temporary traffic controls in place for final cleanup and punch list items.


ODDIE/WELLS PROJECT – PYRAMID WAY (SPARKS) TO I-80 WESTBOUND RAMPS (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. – (775) 335-1861

Phase 1 – Pyramid Way to Sullivan Lane (Sparks):

  • Intermittent lane shifts for punch item list work and landscape work.

Phase 2 – Sullivan Lane (Sparks) to east of US 395 Ramps (Reno):

  • Intermittent lane shifts for punch item list work and landscape work.

Phase 3 – east of US 395 Ramps to Sutro Street (Reno):

Phase 4 – Sutro Street to I-80 Ramps (Reno):

  • Intermittent lane shifts for fiber installation, punch item list work and landscape work.

For additional information on construction status and time-lapse pictures, visit the project website at http://Oddiewellsproject.com


SOUTH VIRGINIA STREET SAFETY & CAPACITY PROJECT – I-580 EXIT 29 TO LONGLEY LANE (RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Two lanes on each direction will remain open along South Virginia Street between 7:00 a.m. to 9:00 a.m. and 4:00 p.m. to 6:00 p.m.
  • Construction during the day. Concrete work (sidewalk, curb, and gutter, driveways, etc.) along the northbound side of South Virginia.
  • Night work is anticipated in August, with closures and detours. At least one lane will be open on South Virginia Street starting at 6:00 p.m. everyday until 7:00 a.m. the next day.


SELMI DRIVE REHABILITATION PROJECT (SUTRO STREET TO CLEAR ACRE LANE RENO)
RTC Project Manager, Maria Paz Fernandez, P.E. -(775) 335-1861

  • Project is substantially complete.
  • All traffic lanes are open in both directions.


STANFORD WAY REHABILITATION PROJECT (GREG STREET TO GLENDALE AVENUE)
RTC Project Manager, Kim Diegle, P.E. – (775) 335-1844

This project is substantially complete.


TRAFFIC SIGNAL INSTALLATIONS 23-01
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Work is substantially complete at the Moana Lane/ Baker Lane, and Prater Way/ 4th Street intersections. Motorists may see occasional shoulder and lane closures for final work items.


SPARKS INTELLIGENT CORRIDORS
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880

Work is substantially completed on Baring Boulevard, Los Altos Parkway, and Vista Boulevard. Additional work to install fiber optic along Galleria Parkway is expected to begin in July.


STEAMBOAT PARKWAY IMPROVEMENT PROJECT – DAMONTE RANCH PARKWAY TO VETERANS PARKWAY
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction is underway and will continue through Fall 2024.

July 8 – July 12

  • Two travel lanes in each direction will be maintained on Steamboat Parkway.
  • Shoulder closure for westbounnd and eastbound Steamboat Parkway between Marketplace Drive and Veterans Parkway.
  • Shoulder closures/lane reduction at the intersection of Veterans Parkway and Steamboat Parkway.


SOUTH MEADOWS TRAFFIC ENHANCEMENTS
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

  • Single lane closure on eastbound South Meadows Parkway between Double R Boulevard and Veterans Parkway near I-580.


NORTH VIRGINIA UNIVERSITY REHABILITATION – LAWLOR ROUNDABOUT TO NORTH MCCARRAN BOULEVARD
RTC Project Manager, Bryan Byrne, P.E. – (775) 3351865

Construction is expected to begin May 28.

June 8 to July 14

  • One travel lane in each direction will be maintained on Virginia Street.
  • Shoulder closures for southbound and northbound traffic through project limits.
  • No on-street parking.

TRAFFIC SIGNAL MODIFICATION 23-01
RTC Project Manager, Sara Going, P.E. – (775) 3351897

Work will begin on the project on July 14 at the following project locations:

Clear Acre Lane and N. McCarran Boulevard

  • Nighttime (6:00 p.m. – 6:00 a.m.) should and lane closures will begin on the evening of Sunday, July 14.
  • At least one lane will remain open on all approaches to the intersection.

El Rancho Drive and G Street

Motorists should anticipate daytime shoulder and lane closures beginning Monday, July 15.

Motorists should anticipate changing lane patterns approaching these intersections. At least one lane for each travel direction will remain open throughout this phase of work.