SIERRA ST / 9TH ST INTERSECTION IMPROVEMENT PROJECT

Project Overview

Label Value
Status Upcoming Projects
Project Details 0215009
RTC Project Manager (PM) LaShonn Ford, P.E.
RTC Engineering Department (775) 348-0171
Design Firm Wood Rodgers
Construction Contractor To be determined

Project Description

This project will identify and implement improvements to the signalized intersection at Sierra Street / 9th Street and Sierra Street and Maple Street. The goal of the improvements is to improve both the traffic operations and safety at the intersections through geometric, striping, and signal phasing changes. The project will also install overhead Rectangular Rapid Flashing Beacon (RRFB) systems and other crossing improvements at the following locations:

  • Flint Street / Liberty Street
  • Wedge Parkway / UNR Redfield Campus
  • Mayberry Drive / Ferris Drive

Latest News

Preliminary engineering design is underway.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2026
Final Design: Winter 2027
Construction: Spring/Summer 2027

Financial Information

Total Project Estimate: $2,900,000
Funding Source: RTC Fuel Tax

To bid, click here:  https://rtcwashoe.procureware.com/login 