Sparks Boulevard Capacity Improvement (Greg Street to Baring Boulevard)

PROJECT DETAILS
RTC Project No. 227001

RTC Project Manager (PM)
Garrett Rodgers
(775) 332-2139
grodgers@rtcwashoe.com

RTC Engineering Department
(775) 348-0171

Design Firm: ATKINS North America

Construction Contractor: Granite Construction Company (South Phase), To be determined (North Phase)

PROJECT DESCRIPTION
The project will increase safety, add roadway capacity, and improve bicycle and pedestrian facilities by widening Sparks Boulevard between Greg Street and Baring Boulevard.

LATEST NEWS
The RTC in cooperation with the City of Sparks, Nevada Department of Transportation (NDOT), and the Federal Highway Administration (FHWA) is finalizing the Finding of No Significant Impact document. The project team is advancing design for the segment of the project between I-80 and Baring Boulevard (Phase 2).

SCHEDULE
Planning: N/A
Environmental: Spring 2020 – Spring 2021
Preliminary Design: Spring 2021 – Fall 2021
Final Design: Fall 2021 – Final 2023
Construction: to be determined based on funding

FINANCIAL INFORMATION
Total Project Estimate: $71,400,000
Funding Source: RTC Fuel Tax

Post updated on: September 29, 2023

Sparks Boulevard Capacity Improvement (Greg Street to Baring Boulevard) Project Map