WEST FOURTH STREET DOWNTOWN

Status: Active Projects

PROJECT DETAILS
RTC Project No. 0211006

RTC Project Manager (PM)
Scott Gibson, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: Wood Rodgers

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project includes pedestrians, multi-modal and ADA improvements. There are also, intersection improvements at Vine Street and lighting improvements throughout the neon line corridor.

LATEST NEWS
The project will start November 3, 2025, with sidewalk work on the north side of the road, then moving on to the south side. There will be a winter break and the contractor will return to complete the Vine Street intersection and the corridor lighting improvements.

Subscribe for Email Updates

* indicates required

SCHEDULE
Planning: N/A
Environmental: To be determined
Preliminary Design: To be determined
Final Design: February 2025
Construction: April 2025

FINANCIAL INFORMATION
Total Project Estimate:
 $7,221,886.25
Funding Source: RTC Fuel Tax

Post updated on: October 28, 2025

West Fourth Street Downtown Project Map