Status: Active Projects
PROJECT DETAILS
RTC Project No. 0211006
RTC Project Manager (PM)
Scott Gibson, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: To be determined
PROJECT DESCRIPTION
This project includes pedestrians, multi-modal and ADA improvements. There are also, intersection improvements at Vine Street and lighting improvements throughout the neon line corridor.
LATEST NEWS
The project will start November 3, 2025, with sidewalk work on the north side of the road, then moving on to the south side. There will be a winter break and the contractor will return to complete the Vine Street intersection and the corridor lighting improvements.
SCHEDULE
Planning: N/A
Environmental: To be determined
Preliminary Design: To be determined
Final Design: February 2025
Construction: April 2025
FINANCIAL INFORMATION
Total Project Estimate: $7,221,886.25
Funding Source: RTC Fuel Tax
Post updated on: October 28, 2025
West Fourth Street Downtown Project Map