Project Description

This project involves the resurfacing of Galletti Way between Glendale Avenue and Kietzke Lane. The project will be a mill and overlay and will include minor pedestrian and ADA improvements.

Latest News

NCE is the design consultant and design is underway. Construction is expected in May 2026.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: June 2025
Final Design: February 2026
Construction: May 2026

Financial Information

Total Project Estimate: $1,052,035.50
Funding Source: RTC Fuel Tax