2026 PREVENTATIVE MAINTENANCE PROGRAM
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Microsurfacing
| Street | From | To | Date |
| Larkin Circle | Greg Street | Peterbilt | 06/27 |
| Madison Avenue | S. Larkin Circle | N. Larkin Circle North | 06/27 |
| Seventh Street | E/S Robb Drive | W/S Keystone Avenue | 06/29 – 07/01 |
| Sierra Center Parkway | E/S Virginia Street | N/S Maestro Drive | 06/30 |
| Bluestone Drive | N/S Huffaker Lane | N End Pavement | 06/30 |
| Sky Mountain Drive | N/S Summit Ridge Drive | Highland Ditch | 07/02 |
| Sky Valley Drive | N/S Summit Ridge Drive | Highland Ditch | 07/02 |
| Campus Way | N/S Sierra Center Parkway | S Neil Road | 07/02 |
| Maestro Drive | W/S Colbert Drive | W/S Longley Lane | 07/02 |
| Maestro Drive | E/S Longley Lane | SW/S Double R Boulevard | 07/02 |
| Valley Road | N/S Freeway Overpass | S/S Enterprise Way | 07/06 |
| Boomtown-Garson Road | E/S Vespucci Drive | S I-80 Westbound Off Ramp | 07/07 |
| Cabela Drive | S Roundabout | S Verdi Road | 07/08 |
| Las Brisas Boulevard | W/S Robb Drive | E/S Brittania Drive | 07/09 |
| Ninth Street | E/S Wells Avenue | City Limits E of Shoshone | 07/10 |
Pavement Patching
| Street | From | To | Date |
| Seventh Street | E/S McCarran Boulevard | N/S Akard Drive | 06/29 |
Pavement Striping (Night Work 7p.m. – 7a.m.)
| Street | From | To | Date |
| Larkin Circle | E Greg Street | Peterbilt E Driveway | 06/28 |
| Madison Avenue | S Larkin Circle | N Larkin Circle | 06/28 |
| Seventh Street | E/S Robb Drive | W/S Keystone Avenue | 06/29-07/01 |
| Sierra Center Parkway | E/S Virginia Street | N/S Maestro Center | 06/30 |
| Bluestone Drive | N/S Huffaker Lane | N End Pavement | 06/30 |
| Sky Mountain Drive | N/S Summit Ridge Drive | Highland Ditch | 07/02 |
| Sky Valley Drive | N/S Summit Ridge Drive | Highland Ditch | 07/02 |
| Campus Way | N/S Sierra Center Parkway | S Neil Road | 07/02 |
| Maestro Drive | W/S Colbert Drive | W/S Longley Lane | 07/02 |
| Maestro Drive | E/S Longley Lane | SW/S Double R Boulevard | 07/02 |
| Valley Road | N/S Freeway Overpass | S/S Enterprise Way | 07/06 |
| Boomtown-Garson Road | E/S Vespucci Drive | S I-80 W Off Ramp | 07/07 |
| Cabela Drive | S Roundabout | S Verdi Road | 07/08 |
| Las Brisas Boulevard | W/S Robb Drive | E/S Brittania Drive | 07/09 |
| Ninth Street | E/S Wells Avenue | City Limits E Of Shoshone | 07/12 |
Thermoplastic
| Street | From | To | Date |
| Los Altos Parkway | Vista Boulevard | Goodwin Road | 06/29 |
| S El Rancho Drive | S Wedekind Road | S McCarran Boulevard | 06/29-06/30 |
| El Rancho Drive | Oddie Boulevard | N/E Greenbrae Drive | 06/29-07/01 |
| Greenbrae Drive | Pyramid Way | 4th Street | 06/30-07/02 |
| E Del Webb Parkway | Somersett Ridge Parkway | Somersett Parkway | 07/02, 7/6-7/8 |
| W Del Webb Parkway | Somersett Ridge Parkway | Somersett Parkway | 07/02, 7/6-7/8 |
| Oddie Boulevard | Mall Drive | W/E Pyramid | 06/07-07/10 |
Crack Sealing (Night Work 7p.m. – 7a.m.)
| Street | From | To | Date |
| Wingfield Hills Road | E David Allen Parkway | N/W Rolling Meadows Drive | 06/28-07/02 |
| E Prater Way | E Sparks Boulevard | City Limits | 06/28-07/02 |
| Lillard Drive | Brierley Way | E Prater Way | 06/28-07/02 |
| E Lincoln Way | Stanford Way | N McCarran Boulevard | 06/28-07/02 |
| E Lincoln Way | Sparks Boulevard | Lillard Drive | 06/28-07/02 |
| Hulda Court | Hulda Way | CDS | 06/28-07/02 |
| Franklin Way | Spice Islands Drive | Kleppe Lane | 06/28-07/02 |
| Deming Way | Spice Islands Drive | Dead End | 06/28-07/02 |
| Purina Way | Spice Islands Drive | E Greg Street | 06/28-07/02 |
| United Circle | W Spice Islands Drive | E Spice Islands Drive | 06/28-07/02 |
| Spice Islands Court | Spice Islands Drive | Cul De Sac | 06/28-07/02 |
| Snider Way | Stanford Way | W Steneri Way | 06/28-07/02 |
| Dermody Way | Glendale Avenue | Dead End | 06/28-07/02 |
| Clean Water Way | E/S McCarran Boulevard | E Cor Soi | 06/28-07/02 |
| Southeast Connector | N Pembroke Drive | N Clean Water Way | 06/28-07/02 |
| Mill Street | Terminal Way | W/S McCarran Boulevard | 07/05-07/09 |
| Terminal Way | N/S Plumb Lane | S Mill Street | 07/05-07/09 |
| Peckham Lane | E/S Virginia Street | W/S Longley Lane | 07/05-07/09 |
| State Street | E/S Virginia Street | W/S Holcomb Avenue | 07/05-07/09 |
| Third Street | W/S Sierra Street | E/S Vine Street | 07/05-07/09 |
| First Street | E/S Center Street | W/S Lake Street | 07/05-07/09 |
| Fourth Street | E/S Virginia Street | W/S Evans Avenue | 07/05-07/09 |
| Sutro Street | S Commercial Row | S Fourth Street | 07/05-07/09 |
| Victorian Avenue | E Prater Way | E El Rancho Boulevard | 07/05-07/09 |
| El Rancho Boulevard | N/E Victoriian Avenue | S/E Prater Way | 07/05-07/09 |
| El Rancho Boulevard | N/E Greenbrae Drive | S/E Wedekind Road | 07/05-07/09 |
| El Rancho Boulevard | McCarran Boulevard | S/E Sullivan Drive | 07/05-07/09 |
| North Hills Boulevard | N/S Golden Valley Road | S Buck Drive | 07/05-07/09 |
| Bridge Street | N Verdi Road | S Third Street | 07/05-07/09 |
| Robb Drive | Sharlands Avenue | S Las Brisas Boulevard | 07/05-07/09 |
7TH STREET, 6TH STREET, & WEST REHABILITATION PROJECT
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861
7th Street Between Keystone Avenue and Washington Street
- Construction is substantially complete.
- Crews will remobilize on 7th Street near Keystone for work in the median, and 7th Street will have one-way westbound travel from Washington Street to Keystone Avenue tentatively scheduled for the week of July 6th.
6th Street between Arlington Avenue and West Street & West Street between 5th Street and 6th Street
- Construction is substantially complete.
BUCK DRIVE ROADWAY IMPROVEMENTS
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
Work Description:
This project will be completed in multiple phases. Initial work includes concrete and roadway improvements on the south side of the roadway.
Traffic Impacts:
- Traffic control will be in place with modified travel patterns.
- 1-way traffic for eastbound traffic on Buck Drive
- Access is limited to the Grocery Outlet Delivery Driveway.
Additional Information:
- Construction activities may impact bus routes and commute times.
- Traffic control will be adjusted as feasible to reduce peak hour impacts.
EAGLE CANYON SAFETY AND OPERATIONS PROJECT
RTC Project Manager, LaShonn Ford, P.E. – (775) 332-2136
Work Description:
Crews are completing roadway electrical work in preparation for new lighting at enhanced crosswalk locations. Site preparation and grading is also underway for construction of the shared-use path from Calle De La Plata to Alena Way.
Traffic Impacts:
Working hours are between 7a.m. and 7p.m.
- On Eagle Canyon Drive expect shoulder closures and/or lane shifts in both directions from Eagle Canyon Park to Calle De La Plata. This closure includes the bicycle lane, so please remember to use caution and share the road with bicycles.
- Travel lanes on Eagle Canyon Drive may be reduced intermittently near Eagle Canyon Park. Access to Eagle Canyon Park will remain open with flagger control. Please use caution and follow flagger instructions.
- Truckee Meadows Water Authority has a concurrent project on Goldeneye Parkway that may cause additional impacts. This may include lane shifts or flagger control on Eagle Canyon Drive. Access to Goldeneye Parkway may be closed from Eagle Canyon Drive. Please use caution in the area.
LA POSADA REHABILITATION
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
Work Description:
Roadway rehabilitation work is underway on La Posada Drive and Cordoba Boulevard. Motorists should expect lane reductions, temporary traffic control, and periodic detours during paving operations.
- La Posada Drive between Pyramid Way and Cordoba Boulevard reduced to one lane in each direction during construction activities. Short-duration full closures and detours may be implemented during paving operations.
- Cordoba Boulevard between La Posada Drive and Calle De Oro Parkway may experience lane closures and intersection detours during roadway rehabilitation work.
Please use caution when traveling through the work zone and follow all posted traffic control devices.
MILITARY ROAD CAPACITY AND SAFETY PROJECT
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Traffic will be shifted on Military Road to allow for two-way traffic with one lane in each direction.
MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane Closures
Construction is substantially complete, but single lane closures may occur on Mill Street from Yori Way to Terminal Way with left turn lanes at all signalized intersections. Closures on Kietzke Lane in the vicinity may also take place.
Signal at Golden Lane
The new traffic signal at Mill Street and Golden Lane is now operational. Please use caution when driving through this area.
Visit MillStreetWidening.com for information and updates.
PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane Closures
On Prater Way from Pyramid Way to Stanford Way, lanes will be reduced to 1 lane in each direction 24/7.
SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction will continue through June 2027. Project limits are from the intersection of Sparks Boulevard/I-80 westbound ramps to the intersection of Sparks Boulevard/Shadow Lane.
The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com) or by texting “Sparks” to 866-540-8466.
Construction operations will mostly take place from 5a.m. – 2p.m. in the northbound direction and 9a.m. – 7p.m. in the southbound direction, Monday through Friday. Nighttime work and marathon weekend work are anticipated, with traffic control updates communicated in advance of this work.
June 28 – July 4
The community can expect the following traffic control:
Northbound and Southbound Long-Term Closure (24/7 thru June 2026)
- 24/7 single lane closure Sparks Boulevard between Prater Way and the Baring Boulevard Intersection in the northbound direction. Closure in effect through June 2026.
- 24/7 single lane closure Sparks Boulevard between Shadow Lane and Prater Way Intersections in the southbound direction. Closure in effect through June 2026.
- 24/7 Single lane closure Sparks Boulevard from I-80 to Lincoln Way northbound direction. I-80 eastbound off-ramp lane restrictions.
Southbound (9a.m. – 7p.m. Monday – Friday)
- Single lane closure Sparks Boulevard from Prater Way to Lincoln Way.
Northbound (5a.m. – 2p.m. Monday – Friday)
- Single lane closure Sparks Boulevard Lincoln Way to Prater Way
Howard Drive Detour:
- Howard Drive closed at Sparks Boulevard. Detour available via Fargo Way to O’Callaghan Drive
TRAFFIC SIGNAL MODIFICATIONS 25-01
RTC Project Manager, LaShonn Ford, P.E. – (775) 332-2136
The project is substantially complete. Crews will be completing remaining roadway striping items throughout June.
VIRGINIA LINE BRT IMPROVEMENTS PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane Closures
Construction has begun Sunday nights to Friday mornings from 7p.m. to 7a.m. Lanes on S. Virginia Street will be reduced to one lane in each direction from Moana Lane to Hubbard Way.
Daytime work at the northbound and southbound Bus Stations at Peckham Lane will occur. Two lanes in each direction will remain open on Virginia Street, but lanes may be shifted. Please use caution.
Gentry Way Intersection
Through traffic on Gentry Way at Virginia Street may be detoured from 7p.m. to 7a.m.
WEST FOURTH STREET DOWNTOWN (WEST STREET TO VINE STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Project is substantially complete. Don’t miss the “4th on Fourth Parade”, July 4th, at 10a.m. to see all the new improvements!
WEST FOURTH STREET SAFTEY (VINE STREET TO MCCARRAN BOULEVARD)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Traffic has been shifted to the south side of Fourth street with two-way traffic in one lane each direction in the four lane areas. The signals at Stoker Avenue have been removed and there is now a three-way stop sign control at Stoker Avenue as well as Summit Ridge Drive. The north side of the roadway will be a work zone throughout the corridor. In the two-lane area west of Summit Ridge Drive, traffic will be primarily two-way as well, with occasions of flagger control when work encroaches on the westbound lane. Work is progressing throughout the corridor. Please slow down so everyone goes home safe!
WHITE FIR STREET REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Traffic will be shifted on White Fir Street to allow for two-way traffic with one lane in each direction.