Status: Active Projects
PROJECT DETAILS
RTC Project No. 245010
RTC Project Manager (PM)
LaShonn Ford, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: GCW, Inc.
Construction Contractor: Titan Electrical Contracting, Inc.
PROJECT DESCRIPTION
Traffic signal, safety, and/or geometric improvements at the following intersections:
Robb Drive and Seventh Street near McQueen High School (In-Progress)
- Replace the static school zone signs with an overhead flashing beacon system to improve speeding compliance and safety.
- Install pedestrian ramps at the midblock crossing on Seventh Street east of Sapphire Ridge Way.
Mayberry Drive / Hunter Lake (In-Progress)
- Replace the static school zone signs with a flashing beacon system to improve speeding compliance and safety.
- Upgrade the emergency vehicle flasher for Reno Fire Station No. 5.
Greg Street / Kleppe Lane (In-Progress)
- Replace traffic signal equipment that has reached end of life.
Baring Boulevard / North Truckee Lane (In-Progress)
- Replace traffic signal poles and equipment that has reached end of life.
- Replace pedestrian ramps.
El Rancho Drive / Wedekind Road (Begins December 1)
- Upgrade the northbound/southbound left-turn signal heads to allow for a flashing yellow arrow.
- Replace the pedestrian ramps on the east side of the intersection.
- Replace traffic signal equipment that has reached end of life.
Baring Boulevard / Goldy Way (Start Date TBD))
- Replace traffic signal poles and equipment that have reached end of life.
- Improve lane alignment and striping.
- Replace pedestrian ramps.
US 395 / Clear Acre Lane (Start Date TBD)
- Modify the signal’s vehicle detection system to induction loops.
Robb Drive / Mae Anne Avenue (Start Date TBD)
- Modify left-turn signal phasing for southbound Robb Drive. Change the shared through/left lane to through only to allow more vehicle movements to run concurrently and improve intersection efficiency.
McCarran Boulevard / Mira Loma Drive (Start Date TBD)
- Add a right-turn signal phase to the McCarran Boulevard northbound right turn. This will improve efficiency by giving the right-turning a dedicated phase that can overlap with other non-conflicting intersection movements.
Calle de la Plata / Isidor Court / Silent Sparrow Drive (Start Date TBD)
- Add a right-turn signal phase to the Silent Sparrow Drive eastbound right-turn. This will improve efficiency by giving the right-turning a dedicated phase that can overlap with other non-conflicting intersection movements.
LATEST NEWS
Construction is underway at several locations. Crews are working intermittently as weather allows.
SCHEDULE
Planning: N/A
Environmental: N/A
Preliminary Design: Fall 2024
Final Design: Spring 2025
Construction: Fall 2025
FINANCIAL INFORMATION
Total Project Estimate: $2,820,371.00
Funding Source: RTC Fuel Tax
Post updated on: December 30, 2025