SPARKS BOULEVARD/ION DRIVE TRAFFIC SIGNAL
Project Overview
| Label | Value |
|---|---|
| Status | Active Projects |
| Project Details | 0225005 |
| RTC Project Manager (PM) | LaShonn Ford, P.E. |
| RTC Engineering Department | (775) 332-2136 |
| Design Firm | GWC, Inc. |
| Construction Contractor | Sierra Nevada Construction, Inc. |
Project Description
This project will construct a new traffic signal on Sparks Boulevard at the Ion Drive / Sawgrass Lane intersection in order to improve safety and traffic operations.
Latest News
Working hours are weekdays from 7:00 AM to 5:00 PM.
Roadway improvements have been completed on the Ion Drive side of the intersection. Crews will complete improvements on the Sawgrass Lane side of the intersection by mid-September. There may be a pause in work while we wait for signal equipment to be delivered. The project will be fully complete sometime in early Fall 2026.