Status: Upcoming Projects
PROJECT DETAILS
RTC Project No. 245011
RTC Project Manager (PM)
Alex Wolfson, P.E.
RTC Engineering Department
(775) 348-0171
Design Firm: Wood Rodgers
Construction Contractor: To be determined
PROJECT DESCRIPTION
This project will make the following improvements:
North McCarran Boulevard / York Way:
- Efficiency improvements on the east and west approaches
- Improve signal head visibility on McCarran southbound
Rock Boulevard / Greg Street
- Convert southbound left turn to improve safety
Rock Boulevard / Commerce Street
- Upgrade existing pedestrian crossing system to rapid rectangular flashing beacons (RRFBs)
Galleria Parkway / Costa Azul Drive
- Improve signal head visibility on Galleria southbound
California Avenue / Plumas Street
- Install dedicated left turn signals for all four intersection approaches
Kietzke Lane / Neil Road
- Install RRFBs at the roundabout crosswalks
South McCarran Boulevard / Caughlin Parkway / Cashill Boulevard
- Install active advanced warning system for McCarran Boulevard southbound due to limited sight distance
LATEST NEWS
The RTC has selected Wood Rodgers to perform design services on this project. Design is now underway.
SCHEDULE
Planning: Fall 2024
Environmental: N/A
Preliminary Design: Winter 2024 – Spring 2025
Final Design: Summer 2025 – Winter 2025
Construction: Spring 2026
FINANCIAL INFORMATION
Total Project Estimate: $1,750,000
Funding Source: RTC Fuel Tax
Post updated on: December 27, 2024
Traffic Signal Modifications 26-01 (Various Roads) Project Map