TRAFFIC SIGNAL MODIFICATIONS 26-01

Status: Upcoming Projects

PROJECT DETAILS
RTC Project No. 245011

RTC Project Manager (PM)
Alex Wolfson, P.E.

RTC Engineering Department
(775) 348-0171

Design Firm: Wood Rodgers

Construction Contractor: To be determined

PROJECT DESCRIPTION
This project will make the following improvements:

North McCarran Boulevard / York Way:

  • Efficiency improvements on the east and west approaches
  • Improve signal head visibility on McCarran southbound

Rock Boulevard / Greg Street

  • Convert southbound left turn to improve safety

Rock Boulevard / Commerce Street

  • Upgrade existing pedestrian crossing system to rapid rectangular flashing beacons (RRFBs)

Galleria Parkway / Costa Azul Drive

  • Improve signal head visibility on Galleria southbound

California Avenue / Plumas Street

  • Install dedicated left turn signals for all four intersection approaches

Kietzke Lane / Neil Road

  • Install RRFBs at the roundabout crosswalks

South McCarran Boulevard / Caughlin Parkway / Cashill Boulevard

  • Install active advanced warning system for McCarran Boulevard southbound due to limited sight distance

LATEST NEWS
The RTC has selected Wood Rodgers to perform design services on this project. Design is now underway.

SCHEDULE
Planning: Fall 2024
Environmental: N/A
Preliminary Design: Winter 2024 – Spring 2025
Final Design: Summer 2025 – Winter 2025
Construction:  Spring 2026

FINANCIAL INFORMATION
Total Project Estimate: $1,750,000
Funding Source: RTC Fuel Tax

Post updated on: December 27, 2024

Traffic Signal Modifications 26-01 (Various Roads) Project Map