PYRAMID HIGHWAY OPERATIONS IMPROVEMENTS
Project Overview
| Label | Value |
|---|---|
| Status | Active Projects |
| Project Details | 0237002 |
| RTC Project Manager (PM) | Jessica Dover, P.E. |
| RTC Engineering Department | (775) 335-1831 |
| Design Firm | Atkins North America Inc. |
| Construction Contractor | Q&D Construction |
Project Description
RTC’s Pyramid Hwy Operations Improvements Project is underway. This Project will construct an additional southbound through lane along SR 445 from Ingenuity Ave to Egyptian Dr, upgrade the traffic signal system at the Calle De La Plata intersection, install a new signal at the Ingenuity Ave intersection, and perform utility adjustments, grading and drainage improvements as necessary.
Construction is anticipated to continue through Spring 2027.
Latest News
Q&D is working toward an interim solution to accommodate detection needs at Calle De La Plata to assist with congestion in the Pyramid Hwy southbound direction work progresses for the project.
Work near the regional culvert is tentatively scheduled to be complete in September 2026.
Paving on Pyramid Hwy is tentatively scheduled to start in October 2026.