SMITHRIDGE REHABILITATION

Project Overview

Label Value
Status Upcoming Projects
Project Details 212086
RTC Project Manager (PM) Bryan Byrne, P.E.
RTC Engineering Department (775) 335-1865
Design Firm DOWL
Construction Contractor To be determined

Project Description

The Smithridge Drive Rehabilitation project will improve the corridor between McCarran Boulevard and Peckham Lane. Work includes pavement rehabilitation, ADA upgrades, curb and sidewalk replacement, and utility modifications.

Latest News

The project team is beginning with data collection and advancing toward development of the fifty percent design package.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Spring 2026
Final Design: Fall 2026
Construction: 2027

Financial Information

Total Project Estimate: $6,917,800.00
Funding Source: RTC Fuel Tax