Skip to main content

TRAFFIC SIGNAL MODIFICATIONS 26-01

Project Overview

Label Value
Status Active Projects
Project Details 245011
RTC Project Manager (PM) Alex Wolfson, P.E., PTOE, RSP1
RTC Engineering Department 775-335-1880
Design Firm Wood Rodgers
Construction Contractor Sierra Nevada Construction

Project Description

This project will make the following improvements:

North McCarran Boulevard / York Way:

Efficiency improvements on the east and west approaches
Improve signal head visibility on McCarran southbound

Rock Boulevard / Greg Street

Convert southbound left turn to improve safety

Rock Boulevard / Commerce Street

Upgrade existing pedestrian crossing system to rapid rectangular flashing beacons (RRFBs)

Galleria Parkway / Costa Azul Drive

Improve signal head visibility on Galleria southbound

California Avenue / Plumas Street

Install dedicated left turn signals for all four intersection approaches

Kietzke Lane / Neil Road

Install RRFBs at the roundabout crosswalks

South McCarran Boulevard / Caughlin Parkway / Cashill Boulevard

Install active advanced warning system for McCarran Boulevard southbound due to limited sight distance

Latest News

Large scale construction on this project will occur in the first half of 2027 with some smaller sections of work occurring earlier.

Schedule

Planning: Fall 2024
Environmental: N/A
Preliminary Design: Winter 2024 – Spring 2025
Final Design: Summer 2025 – Winter 2025
Construction:  Summer 2027

Financial Information

Total Project Estimate: $3,568,737
Funding Source: RTC Fuel Tax

Project Map