VISTA BOULEVARD/DISC DRIVE INTERSECTION IMPROVEMENT

Project Overview

Label Value
Status Active Projects
Project Details 247013
RTC Project Manager (PM) Alex Wolfson, P.E., PTOE, RSP1
RTC Engineering Department (775) 335-1880
Design Firm Wood Rodgers
Construction Contractor Sierra Nevada Construction

Project Description

This project will make the following improvements at the Vista Boulevard and Disc Drive intersection:

  • Construct a southbound Vista Boulevard to westbound Disc Drive dedicated right-turn lane
  • Construct a westbound Disc Drive to southbound Vista Boulevard dedicated left-turn lane
  • Extend the eastbound Disc Drive to northbound Vista Boulevard left-turn lane

Latest News

All construction is now complete, this will be the final project update.

Schedule

Planning: N/A
Environmental: N/A
Preliminary Design: Spring/Summer 2024
Final Design: Summer/Fall 2024
Construction: Spring 2025 through 2026

Financial Information

Total Project Estimate: $2,527,819.00
Funding Source: RTC Fuel Tax