WEST FOURTH STREET DOWNTOWN

Project Overview

Label Value
Status Active Projects
Project Details 0211006
RTC Project Manager (PM) Scott Gibson, P.E.
RTC Engineering Department (775) 335-1874
Design Firm Wood Rodgers
Construction Contractor To be determined

Project Description

This project includes transit stations, pedestrian and ADA improvements. There are also, intersection improvements at Vine Street and lighting improvements throughout the neon line corridor.

Latest News

The contractor has completed most of the ADA improvements, sidewalk, and landscape work on the north side of Fourth Street and moved on to the south side. Work is expected to be complete in late Spring 2026.

Subscribe for Updates

* indicates required

Visit the Project Website

More information is available at fourthstreetimprovements.com

Schedule

Planning: N/A
Environmental: To be determined
Preliminary Design: To be determined
Final Design: February 2025
Construction: April 2025

Financial Information

Total Project Estimate: $7,221,886.25
Funding Source: RTC Fuel Tax