WEST FOURTH STREET SAFETY

Project Overview

Label Value
Status Active Projects
Project Details 0713001
RTC Project Manager (PM) Scott Gibson, P.E.
RTC Engineering Department (775) 335-1874
Design Firm Wood Rodgers
Construction Contractor Sierra Nevada Construction (SNC)

Project Description

The focus of this project is to provide safety improvements to Fourth Street between McCarran Boulevard and Keystone Avenue. Improvements include roundabouts at Stoker Avenue and Summit Ridge Drive, lane reductions, a multi-use path and pavement rehabilitation.

Latest News

RTC has awarded the construction to Sierra Nevada Construction (SNC) and the construction management contract to CME, Inc. Construction is underway with significant traffic control systems in place. One way configurations will be implemented in the following weeks as roadwork nears completion. Slow down for workers!

Visit the Project Website

More information is available at www.fourthstreetimprovements.com

Schedule

Planning: N/A
Environmental: November 17 2023
Preliminary Design: May 17, 2024
Final Design: July 26, 2024
Construction: February 15, 2026

Financial Information

Total Project Estimate: $28,345,000
Funding Source: Federal Highway Safety Improvement Program (HSIP)