2026 PREVENTATIVE MAINTENANCE PROGRAM
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Microsurfacing
| STREET | FROM | TO | DATE |
| Del Webb Parkway East | Somersett Ridge Parkway | Somersett Parkway | 06/22-23 |
| Del Webb Parkway West | Somersett Ridge Parkway | Somersett Parkway | 06/22-23 |
| Oddie Boulevard | Mall Drive | Pyramid Way | 06/24-25 |
| Western Skies Drive | Equestrian Road | Reading Street | 06/26 |
| Larkin Circle | Greg Street | Peterbilt Way | 06/27 |
| Madison Avenue | Larkin Circle | Larkin Circle | 06/27 |
Pavement Striping (Night Work 7pm – 7am)
| STREET | FROM | TO | DATE |
| Del Webb Parkway East | Somersett Ridge Parkway | Somersett Parkway | 06/22-23 |
| Del Webb Parkway West | Somersett Ridge Parkway | Somersett Parkway | 06/22-23 |
| Oddie Boulevard | Mall Drive | Pyramid Way | 06/24-25 |
| Western Skies Drive | Equestrian Road | Reading Street | 06/26 |
| Larkin Circle | Greg Street | Peterbuilt Way | 06/28 |
| Madison Avenue | Larkin Circle | Larkin Circle | 06/28 |
Theroplastic
| STREET | FROM | TO | DATE |
| S 15th Street | Hymer Avenue | Glendale Avenue | 06/22 |
| S 16th Street | Glendale Avenue | Hymer Avenue | 06/22 |
| S 18th Street | Glendale Avenue | Crane Way | 06/22 |
| S 19th Street | Alley | Pacific Avenue | 06/22 |
| David Allen Parkway | Kiley Parkway | Fortunato Loop | 06/22-24 |
| Los Altos Parkway | Vista Boulevard | Goodwin Road | 06/24-26 |
Traffic Loop Installation
| STREET | FROM | TO | DATE |
| Veterans Parkway | Geiger Grade Roundabout | South Meadows Parkway | 06/22 |
Crack Sealing (Night Work 7:00 p.m. – 7:00 a.m.)
| STREET | FROM | TO | DATE |
| Country Club Drive | Tahoe Boulevard | South Side S. R. 431 | 06/21-25 |
| Lakeshore Boulevard | Village Boulevard | S.R. 28 | 06/21-25 |
| Incline Way | N Side Country Club | Southwood Boulevard | 06/21-25 |
| Tanager Street | West Side Village Boulevard | Southwood Boulevard | 06/21-25 |
| Northwood Boulevard | N Side of S.R 28 | N of S.R. 28-E Int | 06/21-25 |
| Eastlake Boulevard | 1750 ft S. Cattleguard | 505 Ft S. Coyote Drive | 06/21-25 |
| Thomas Creek Road | Holcomb Lane | Foothill Road | 06/21-25 |
| Hawco Court | Ingenuity Avenue | Ingenuity Avenue | 06/21-25 |
| Ingenuity Aveenue | W Side of St 445 | Hawco Court | 06/21-25 |
| Isidor Court | Circuit Court | Academy Way | 06/21-25 |
| Distribution Drive | Calle de la Plata | Isudor Court | 06/21-25 |
| Inventors Place | Isidor Court | Isidor Court | 06/21-25 |
| Circuit Court | Isidor Court | Isidor Court | 06/21-25 |
| Digital Court | Ingenuity Avenue | Ingenuity Avenue | 06/21-25 |
| La Posada Drive | Cordoba Boulevard | End of Curb | 06/21-25 |
| Wingfeild Hills Road | David Allen Parkway | Rolling Meadows Drive | 06/21-25 |
7TH STREET, 6TH STREET, & WEST REHABILITATION PROJECT
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861
7th Street Between Keystone Avenue and Washington Street
- Construction is substantially complete. Crews may be intermittently working on miscellaneous clean up on-site.
- Crews will remobilize on 7th Street near Keystone for work in the median, and 7th Street will have one-way westbound travel from Washington Street to Keystone Avenue at a time and duration to be determined.
- Parking on the south side of 7th Street between Keystone Street and Washington Aveneue is prohibited in the new bike lane.
6th Street between Arlington Avenue and West Street & West Street between 5th Street and 6th Street
- Construction is substationaly complete. Crews may be intermittently working on miscellaneous clean up on-site.
BUCK DRIVE ROADWAY IMPROVEMENTS
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
Work Description
This project will be completed in multiple phases. Initial work includes concrete and roadway improvements on the south side of the roadway.
Traffic Impacts
- Traffic control will be in place with modified travel patterns.
- 2-way traffic on Buck Drive and N. Hills Boulevard.
- Access is limited to the Grocery Outlet Delivery Driveway.
Additional Information
- Construction activities may impact bus routes and commute times.
- Traffic control will be adjusted as feasible to reduce peak hour impacts
EAGLE CANYON SAFETY AND OPERATIONS PROJECT
RTC Project Manager, LaShonn Ford, P.E. – (775) 332-2136
Working hours are between 7:00 a.m. and 7:00 p.m.
On Eagle Canyon Drive expect shoulder closures in the both directions from Richard Springs Drive to Calle de la Plata. The outside travel lane in the westbound direction will be closed from east of the Richard Springs Drive intersection to the Eagle Landing shopping center roundabout. This closure includes the bicycle lane. Please remember to use caution and share the road with bicycles.
Truckee Meadows Water Authority has a concurrent project on Goldeneye Parkway that may cause additional impacts. This may include lane shifts or flagger control on Eagle Canyon Drive. Access to Goldeneye Parkway may be closed from Eagle Canyon Drive. Please use cation in the area.
LA POSADA REHABILITATION
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
Work Description
Roadway rehabiliation work is underway on La Posada Drive and Cordoba Boulevard. Motorists should expect lane reductions, temporary traffic control, and periodic detours during paving operations.
- La Posaada Drive between Pyramid Way and Cordoba Boulevard reduced to one lane in each direction during cnostruction activities. Short-duration full closures and detours may be implemented during paving operations.
- Cordoba Boulevard between La Posada Drive and Calle de Oro Parkway may experience lane closures and intersection detours during roadway rehabiltation work.
MILITARY ROAD CAPACITY AND SAFETY PROJECT
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Construction begins June 15th. Traffic will be shifted to allow for two-way traffic with one lane in each direction.
MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane Closures
Construction is substantially complete, but single lane closures may occur on Mill Street from Yori Way to Terminal Way with left turn lanes at all signalized intersections. Closures on Kietzke Lane in the vicinity may also take place. Short traffic delays may occur during some operations.
Signal at Golden Lane
The new traffic signal at Mill Street and Golden Lane is now operational. Please use caution when driving through this area.
Visit MillStreetWidening.com for information and updates.
PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane Closures
Roadway construction on Prater Way will begin on June 15. From Pyramid Way to Standofr Way, lanes will be reduced to one(1) lane in each direction from 7:00 a.m. to 5:00 p.m., Monday – Friday.
SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction will continue through June 2027. Project limits are from intersection of Sparks Boulevard/I80 westbound ramps to the intersection of Sparks Boulevard/Shadow Lane.
The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com), or by texting “Sparks” to 866-540-8466.
Construction operations will mostly take place from 5:00 a.m. – 2:00 p.m. in the northbound direction and 9:00 a.m. – 7:00 p.m. in the southbound direction, Monday through Friday. Nighttime work and marathon weekend work are anticipated, with traffic control updates communicated in advance of this work.
June 21 – June 27
The community can expect the following traffic control:
Northbound and Southbound Long-Term Closure (24/7 thru June 2026)
- 24/7 single lane closure Sparks Boulevard between Prater Way and the Baring Boulevard Intersection in the northbound direction. Closure in effect through June 2026.
- 24/7 single lane closure Sparks Boulevard between Shadow Lane and Prater Way Intersections in the southbound direction. Closure in effect through June 2026.
- 24/7 Single lane closure Sparks Boulevard from I-80 to Lincoln Way northbound direction. I-80 eastbound off-ramp lane restrictions.
Southbound (9:00 a.m. – 7:00 p.m., Monday-Friday)
- Single lane closure Sparks Boulevard from Prater Way to Lincoln Way.
Northbound (5:00 a.m. – 2:00 p.m., Monday-Friday)
- Single lane closure Sparks Boulevard Lincoln Way to Prater Way
Howard Drive Detour
- Howard Drive closed at Sparks Boulevard. Detour available via Fargo Way to O’Callaghan Drive.
TRAFFIC SIGNAL MODIFICATIONS 25-01
RTC Project Manager, LaShonn Ford, P.E. – (775) 332-2136
This project is substantially complete. Crews will be completing remining roadway striping items in June.
VIRGINIA LINE BRT IMPROVEMENTS PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane Closures
Construction has begun Sunday nights to Friday mornings from 7:00 p.m. to 7:00 a.m. Lanes on S. Virginia Street will be reduced to one lane in each direction from Moana Lane to Hubbard Way.
Daytime work at the northbound and southbound Bus Stations at Peckham Lane will occur. Two lanes in each direction will remain open on Virginia Street, but lanes may be shifted. Please use caution.
Gentry Way Intersection
Through traffic on Gentry Way at Virginia Street may be detoured from 7:00 p.m. to 7:00 a.m.
WEST FOURTH STREET DOWNTOWN (WEST STREET TO VINE STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
The Fourth Street and Vine Street intersections is open with temporary signal equipment in place. Crews have completed slurry sealing and striping Fourth Street and Vine Street outside of the intersection. Crews will continue installing the new corridor lighting. Some of these lights have been stood up on the south side of Fourth Street between Ralston Street and Arlington Avenue – check it out!. Slow down for workers!
WEST FOURTH STREET SAFTEY (VINE STREET TO MCCARRAN BOULEVARD)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Traffic has been shifted to the southside of Fourth Street with two-way traffic in one lane each direction in the four lane areas. The signals at Stoker have been removed and there is now three-way stop sign control at Stoker as well as Summit Ridge Court. The north side of the roadway will be a work zone throughout the corridor. In the two-lane area west of Summit Ridge Court, traffic will two-way as well with stop control at Summit Ridge Court. There will be occasions of flagger control when work encroaches on the westbound lane. Retaining wall and sidewalk work continues, work is progressing throughout the corridor. Please slow down so everyone goes home safe!
WHITE FIR STREET REHABILITATION
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Traffic will be shifted on White Fir Street to allow for two-way traffic with one lane in each direction.