2026 PREVENTATIVE MAINTENANCE PROGRAM
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
No work scheduled for the week of May 11 – May 15
7TH STREET, 6TH STREET, & WEST REHABILITATION PROJECT
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861
Normal working hours are Monday through Friday 7:00 a.m. – 5:30 p.m.
May 11 – May 15
7th Street Between Keystone Avenue and Washington Street
- Final paving was completed May 8th. Crews will be raising utilities, installing concrete median islands, striping, and placing new signs.
- 7th Street will be closed to eastbound traffic with one-way westbound traffic between Washington Street and Keystone Avenue. Access will be maintained to adjacent properties during construction.
- Vehicles and pedestrians should follow posted detours. Please use alternate routes such as University Terrace.
- Parking on street will not be possible within the construction traffic zones during construction.
- During construction, the RTC RIDE ROUTE 4 bus will be impacted. Detours or changes to bus stop locations are noted in advance of the affected stops.
6th Street between Arlington Avenue and West Street & West Street between 5th Street and 6th Street
- Final paving was completed May 8th. Crews will raising utilities, striping, and placing new signs.
- Vehicles and pedestrians should follow posted detours:
- 6th Street will be closed between Arlington Avenue and West Street.
- One-way southbound traffic on West Street from 6th Street to 5th Street.
- Please use alternate routes such as Arlington Avenue, 5th Street, and Sierra Street.
- Detour route for St. Mary’s Emergency Room will be posted.
Access will be maintained to adjacent properties during construction. Parking on street will not be possible within the construction traffic control zones during construction.
ARLINGTON AVENUE BRIDGES PROJECT – 1ST STREET TO ISLAND AVENUE
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
- Arlington Avenue will close between West 1st Street and Island Avenue.
- Northbound traffic will be detoured to Virginia Street or Center Street.
- Southbound traffic and pedestrians will be detoured to the Sierra Street Bridge.
- West Street will be open to westbound traffic only between West Street and Stevenson Street.
- Wingfield Park will remain closed from May 5, 2025, until summer 2026.
- River recreation detours will also be in place.
- View detour maps at ArlingtonBridges.com
BUCK DRIVE ROADWAY IMPROVEMENTS
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
Work Description
This project will be completed in multiple phases. Initial work includes concrete and roadway improvements on the south side of the roadway improvements on the south side of the roadway.
Traffic Impacts
- Traffic control will be in place with modified travel patterns
- Eastbound travel will be maintained on Buck Drive
- Southbound travel only will be permitted on N. Hill Boulevard
- Westbound access will be maintained west of the Grocery Outlet Delivery Driveway.
Additional Information
- Construction activities may impact bus routes and commute times.
- Traffic control will be adjusted as feasible to reduce peak hour impacts
MILL STREET CAPACITY & SAFETY
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Lane Closures
A minimum of one paved lane will be open in each direction on Mill Street from Yori Avenue to I-580 with left turn lanes at all signalized intersections. Closures on Kietzke Lane in the vicinity may also take place. Short traffic delays may occur during some operations.
Signal at Golden Lane
the new traffic signal at Mill Street and Golden Lane is anticipated to be turned on Wednesday May 13. Short traffic delay may occur during some operations.
Bus Stop Closures
RTC RIDE bus service may be temporarily impacted within the project area. Detours or changes to bus stop locations will be noted in advance at the affected bus stop and at https://rtcwashoe.com/alerts/
In the event of a closure, riders should follow signage to the nearest bus stop of call RTC customer service at (775) 348-RIDE (348-7433) for real time information.
Visit MillStreetWidening.com for information and updates. Text “MillStreet” to 866-540-8466 to sign up for construction text alerts.
SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Construction will continue through June 2027. Project limits are from intersection of Sparks Boulevard/I80 westbound ramps to the intersection of Sparks Boulevard/ Shadow Lane.
The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com), or by texting “Sparks” to 866-540-8466.
Construction operations will mostly take place from 5:00 a.m. – 2:00 p.m. in the northbound direction and 9:00 a.m. – 7:00 p.m. in the southbound direction, Monday through Friday. Nighttime work and marathon weekend work are anticipated, with traffic control updates communicated in advance of this work.
May 10 – May 16
The community can expect the following traffic control:
Northbound and Southbound Long-Term Closure (24/7 thru May 2026)
- 24/7 single lane closure Sparks Boulevard between Baring Boulevard and the Prater Way Intersection. Closure in effect through May 2026.
- 24/7 single lane closure Sparks Boulevard between Baring Boulevard and Shadow Lane Intersections in the Southbound direction only. Closure in effect through May 2026.
- Single lane closure Sparks Boulevard from I-80 to Lincoln Way northbound direction. I-80 eastbound off-ramp lane restrictions.
Southbound (9:00 a.m. – 7:00 p.m., Monday-Friday)
Single lane closure Sparks Boulevard from I-80 to Lincoln Way. I-80 eastbound off-ramp lane restriction.
Howard Drive Detour
Howard Drive closed at Sparks Boulevard. Detour available via Fargo Way to O’Callaghan Drive.
TRAFFIC SIGNAL MODIFICATIONS 25-01
RTC Project Manager, LaShonn Ford, P.E. – (775) 332-2136
May 11 – May 17
Please anticipate major disruptions as crews complete paving work at the following locations:
Baring Boulevard / N. Truckee Lane
Anticipate intermittent lane closures in all directions while crews complete striping.
Baring Boulevard / Goldy Way
Anticipate intermittent lane closures in all directions while crews complete striping.
Calle de la Plata / Silent Sparrow Drive
May 11th: Silent Sparrow Drive between Cygnus Way and Calle De La Plata will be closed temporarily for paving. A signed detour will be in place.
El Rancho Drive / Wedekind Road
Beginning May 16th: Anticipate intermittent lane closures in all directions while crews complete striping.
VISTA AND DISC INTERSECTION IMRPOVEMENT PROJECT
RTC Project Manager, Alex Wolfson, P.E. – (775) 335-1880
May 12 – May 14
Motorists can expect various daily lane closures with flaggers on Vista Boulevard and Disc Drive at the intersection for final striping work. Delays will be likely with this work, and an alternate route should be considered.
WEST FOURTH STREET DOWNTOWN (WEST STREET TO VINE STREET)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
The Fourth Street and Vine Street intersections is open with temporary signal equipment in place. Crews will be slurry sealing on Fourth Street and Vine Street outside of the intersection. ext month crews will continue installing the new corridor lighting. Some of these have been stood up on the south side of Fourth Street between Ralston Street and Arlington Avenue. Slow down for workers!
WEST FOURTH STREET SAFTEY (VINE STREET TO McCARRAN BOULEVARD)
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Traffic has been shifted to the southside of Fourth Street with two-way traffic in one lane each direction in the four lane areas. The signals at Stoker have been removed and there is now three-way stop sign control at Stoker. The north side of the roadway will be a work zone throughout the corridor. In the two-lane area west of Summit Ridge Court, traffic will be eastbound; on Summit Ridge Court traffic will be northbound only. Retaining wall and sidewalk work continues, work will continue to progress throughout the corridor. Please slow down so everyone goes home safe!