September 25, 2026

2026 PREVENTATIVE MAINTENANCE PROGRAM
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

Microsurfacing (Day Work)

STREET FROM TO DATE
South Meadows Parkway Gateway Drive Double Diamond Parkway 10/3-4

 

Utility Adjustments (Day Work)

STREET FROM TO DATE
Boomtown-Garson Road Cabela Drive Fildago Way 09/28
Silver Lake Road Peppermint Drive Black Bear Drive 09/30-10/01
Clasen Court Ingenuity Avenue Cul-de-sac 10/1-2
Richard Springs Drive Shelby Drive David James Boulevard 10/1-2
Disc Drive Sparks Boulevard Harrier Way 10/1-2

BUCK DRIVE ROADWAY IMPROVEMENTS PROJECT
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865

Work Description

This project will be completed in multiple phases. The next phase will implement final striping. The new signal at North Hills Boulevard and Buck Drive will be installed later this fall.

Traffic Impacts

  • Traffic control will be in place with modified travel patterns.
  • Utilize U-turns for business access.

EAGLE CANYON SAFETY AND OPERATIONS PROJECT
RTC Project Manager, LaShonn Ford, P.E., P.T.O.E. – (775) 332-2136

The project is substantially complete. There may be intermittent closures as crews work to complete final items. On behalf of RTC, thank you for your patience throughout the course of construction.   


MILITARY ROAD CAPACITY AND SAFETY PROJECT
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

Traffic will be shifted on Military Road to allow for two-way traffic, with one lane in each direction.

The community is encouraged to stay informed about the project by accessing the project website: rtcwashoe.com/project/military-road-capacity-safety or by calling the Project Hoteline at (775) 235-2686.


PEMBROKE DRIVE CAPACITY AND SAFETY IMPROVEMENTS (MCCARRAN BOULEVARD TO VETERANS PARKWAY)
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861

Construction started September 14th.  Normal working hours are 7:00 a.m. – 5:00 p.m., Monday through Friday.

The first phase of construction will include earthwork on the north side of Pembroke and the installation of underground utilities and storm drain infrastructure.

Minimal traffic impacts are anticipated during the first phase of construction.  The roadway shoulder on the north side of Pembroke will be closed 24-hours a day and intermittenet lane closures will occur to instaill underground infrastrucure across Pembroke Drive.


PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844

Crews continue pavement reconstruction on the north side of Prater Way between Pyramid Way and Stanford Way. 

On Monday, September 21, 4th Street access on the north side of Prater Way will be closed.  Traffic will be detoured to I Street.

Beginning Tuesday, September 22, and through the month of September:

  • Access to and from the north side of Prater Way to 6th Street, Shriver Bouelvard, and 1st Street will be closed.
  • Two-way traffic will be maintaine on Prater Way. 
  • Access to 4th Street will remain open. 
  • Residential driveways will remain accessible with temporary ramps, except for bried periods when construction equipment is active in the area.

PYRAMID HIGHWAY OPERATIONS IMPROVEMENTS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831

September 28 – October 02

Work during the week of 9/28/2026, will generally include construction of drainage improvements including backfilling the wingwall, roadway prep in the southbound and northbound direction and concrete (sidewalk) improvements.

  • Traffic control impacts will include intermittent shoulder closures in both directions, throughout the project limits (Egyptian Drive to Ingenuity Avenue)
  • A minimum of one paved travel lane will be open in each direction
  • Left turn lanes at all signalized intersections will be open
  • Short traffic delays may occur during this phase of construction
  • Access will be maintained to adjacent properties
    • Temporary driveway closures may occur during certain construction activities; and if so, Q & D will provide notice to impacted properties 18-24 hours prior to start of work
  • Normal working hours are from 7:00 a.m. to 7:00 p.m., Monday – Friday
  • Vehicles and pedestrians should follow posted detours and proceed with caution throughout the work zone.

SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139

Construction will continue through June 2027. Project limits are from the intersection of Sparks Boulevard/I-80 westbound ramps to the intersection of Sparks Boulevard/Shadow Lane.

The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com) or by texting “Sparks” to 866-540-8466.

Construction operations will mostly take place from 5:00 a.m. – 2:00 p.m. in the northbound direction and 9:00 a.m. – 7:00 p.m. in the southbound direction, Monday – Friday. Nighttime work and marathon weekend work are anticipated, with traffic control updates communicated in advance of this work.

September 27 – October 03

The community can expect the following traffic control:

Northbound and Southbound Long-Term Closure (24/7 through September 2026)  

  • 24/7 single lane closure Sparks Boulevard between Lincoln Way and Baring Boulevard in the northbound direction.  Closure in effect through September 2026.
  • 24/7 single lane closure Sparks Boulevard between Shadow Lane and Lincoln Way intersections in the southbound direction.  Closure in effect through September 2026. 

Howard Drive Detour:  

  • Howard Drive closed at Sparks Boulevard. A detour is available via Fargo Way to O’Callaghan Drive.

SPARKS BOULEVARD/ION DRIVE TRAFFIC SIGNAL PROJECT
RTC Project Manager, LaShonn Ford, P.E., P.T.O.E – (775) 332-2136

Concrete and paving work at the intersection is complete. Beginning September 21st there will be a pause in work as we wait for signal equipment to arrive.  


TRAFFIC SIGNAL FIBER 26-01 PROJECT
RTC Project Manager, LaShonn Ford, P.E., P.T.O.E – (775) 332-2136

Crews are performing trenching work for the installation of fiber-optic conduit. During daytime working hours the outside lane on El Rancho Drive in the northbound direction will be closed between Greenbrae Drive and Wedekind Road. 


VIRGINIA LINE BRT IMPROVEMENTS PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844

Lane Closures

Construction continues Sundau night to Friday morning from 7:00 p.m. to 7:00 a.m.  Lanes on S. Virginia Street will be reduced to one lane in each direction from Moana Lane to Hubbard Way.

Gentry Way Intersection

Through traffic on Gentry Way at Virginia Street may be detoured from 7:00 p.m. – 7:00 am.

BRT Stations

Northbound and southbound Bus Rapid Transit stations remain closed at McCarran Boulevard and the southbound station at Orchard Plaza.  Shoulder closures are in place at the stations.  Starting Monday, September 21, the southbound Mt. Rose station and the northbound Center Street station will also be closed for reconstruction. Closed stations are temporaily relocated for passenger pickup.  Passengers should follow signage to the nearest available stop.


WEST FOURTH STREET SAFTEY (VINE STREET TO MCCARRAN BOULEVARD) PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874

MAJOR CHANGE! The contractor is starting work on the south side of the roadway and traffic will be shifted to new pavement on the north side of the roadway between Summit Ridge Drive and Keystone Avenue.  In the two-lane area west of Summit Ridge Drive, traffic will be two-way on both old and new pavement.  Work is also beginning on the east side of Keystone Avenue between Keystone Avenue and Vine Street.  Lots of activity throughout the corridor as the contractor continues to make progress. Please slow down so everyone goes home safe! 


WHITE FIR STREET REHABILITATION PROJECT
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824

Traffic will be shifted on White Fir Street to allow for two-way traffic, with one lane in each direction. Please use caution in the area.