2026 PREVENTATIVE MAINTENANCE PROGRAM
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
No work is scheduled.
BIGGEST LITTLE BIKE NETWORK
RTC Project Manager, Sara Going, P.E. – (775) 335-1897
Work This Week
Crews will work on Sinclair Street between Liberty Street and Holcomb Avenue during daytime working hours. Sinclair Street will be closed to through traffic between Moran Street and Holcomb Avenue. Local access will remain open for residents only. Please use caution and follow construction crew directions within the work zone.
BUCK DRIVE ROADWAY IMPROVEMENTS PROJECT
RTC Project Manager, Bryan Byrne, P.E. – (775) 335-1865
Work This Week
The project will be completed in multiple phases. The next phase will include final striping. The new traffic signal at North Hills Boulevard and Buck Drive is anticipated to be installed later this fall.
Traffic Impacts
- Traffic control will remain in place, and drivers should expect modified travel patterns.
- U-turns may be required to access local businesses.
BUS STOP IMPROVEMENTS 26-01 PROEJCT
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861
Work This Week
Crews will be working on bus stops on Wedekind Road between Sutro and Clear Acre.
Traffic Impacts
Eastbound travel lane on Wedekind Road between Sutro Street and Clear Acre Lane will be closed to thru traffic and detours will be in place during working hours, Monday through Friday, 7:00 am – 5:00 pm. Drivers should allow extra travel time and follow posted detours and traffic-control devices.
Eastbound bus stops on Wedekind Road between Sutro Street and Clear Acre Lane will be temporarily closed during working hours, Monday through Friday, 7:00 am to 5:00 pm. Passengers should follow posted signs to the nearest available stop. A temporary bus stop will be located on Tripp Drive before Willow Hills Circle during working hours.
EAGLE CANYON SAFETY AND OPERATIONS PROJECT
RTC Project Manager, LaShonn Ford, P.E., P.T.O.E. – (775) 332-2136
Work This Week
The project is substantially complete. Intermittent closures may occur as crews complete final project items. RTC appreciates the public patience throughout construction.
GALLETTI WAY – KIETZKE LANE TO GLENDALE AVENUE
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Work This Week
Galletti will be fully closed paving operations. This will shorten the construction and lead to early completion. Detours will be off Battle Born Way and 21st Street. 21st Street can be accessed via Rock Boulevard to Hymer Avenue and Glendale Avenue.
MILITARY ROAD CAPACITY AND SAFETY PROJECT
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Work This Week
Traffic will be shifted on Military Road to maintain for two-way traffic, with one lane in each direction. Drivers should follow posted signs and use caution in the area.
Public Information
The community is encouraged to stay informed about the project by accessing the project website: rtcwashoe.com/project/military-road-capacity-safety or by calling the Project Hoteline at (775) 235-2686.
PEMBROKE DRIVE CAPACITY AND SAFETY IMPROVEMENTS (MCCARRAN BOULEVARD TO VETERANS PARKWAY)
RTC Project Manager, Ashley Hurlbut, P.E. – (775) 335-1861
Work This Week
Earthwork on the north side of Pembroke Drive and the installation of underground utilities and storm-drain infrastructure across Pembroke Drive.
Traffic Impacts
The north-side roadway shoulder will be closed 24 hours a day. Intermittent lane closures will occur while crews install underground infrastructure across Pembroke Drive.
One-way travel on Pembroke Drive will be implemented between McCarran Boulevard and Veterans Parkway between 9:00 a.m. – 4:00 p.m. Posted detours will be in place.
Drivers should allow extra travel time and follow posted detours and traffic control devices.
PRATER WAY REHABILITATION PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Work This Week
Crews continue electric utility work and begin roadway pulverization on the south side of Prater Way in preparation for paving on this side.
Traffic Impacts
- Two-way traffic will be maintained on the north side of Prater Way.
- No street parking is allowed from Pyramid Way to Standford Way.
- 6th and 7th Streets will be closed at Prater Way with access off of Wright Way. Other side streets and commercial driveways will remain accessible using temporary ramps, except for brief periods when construction equipment is active in the area.
- Free right turn from northbound Pyramid Way to eastbound Prater Way will be closed.
PYRAMID HIGHWAY OPERATIONS IMPROVEMENTS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Project Information
Construction is anticipated to continue through Spring 2027. The project limits extend from ingenuity Avenue to Egyptian Drive.
Work This Week
During the week of November 9-13, work will include drainage improvements near the Calle De La Plata intersection and median curn construction. Paving will resume on 11/10 and continue for the remainder of the week, weather permitting.
Traffic Impacts
Drivers and pedestrians should follow posted detours and use caution throughout the work zone.
- At least one paved travel lane will remain open in each direction.
- Left turn lanes at all signalized intersections will remain open unless otherwise approved by the RTC.
- Short traffic delays may occur.
- Access to adjacent properties will be maintained.
- Temporary driveway closures may be necessary during certain construction activities. Impacted properties will receive notice from Q&D approximately 18-24 hours before work begins.
- Normal working hours are 7:00 a.m. to 7:00 p.m., Monday – Friday.
SPARKS BOULEVARD CAPACITY IMPROVEMENT PROJECT – NORTH PHASE
RTC Project Manager, Garrett Rodgers, P.E. – (775) 332-2139
Project Information
Construction is anticipated to continue through June 2027. The project limits extend from the Sparks Boulevard/I-80 westbound ramp intersection to the Sparks Boulevard/Shadow Lane intersection.
Traffic Impacts
Construction operations will generally occur:
- Northbound: 5:00 a.m. – 2:00 p.m., Monday – Friday
- Southbound: 9:00 a.m. – 7:00 p.m., Monday – Friday
Nighttime work and work during special events may occur. Additional traffic control information will be provided in advance when applicable.
Work This Week
- 24/7 single-lane closure is anticipated on northbound Sparks Boulevard between Lincoln Way and Baring Boulevard intersection.
- 24/7 single-lane closure is anticipated on southbound Sparks Boulevard between Baring Boulevard and Lincoln Way.
- Howard Drive is closed at Sparks Boulevard. Drivers should use Fargo Way and O’Callaghan Drive as the detour route.
Public Information
The community is encouraged to stay informed about the project by accessing the project website (www.sparksblvdproject.com) or by texting “Sparks” to 866-540-8466.
SPARKS BOULEVARD/ION DRIVE TRAFFIC SIGNAL PROJECT
RTC Project Manager, LaShonn Ford, P.E., P.T.O.E – (775) 332-2136
Work This Week
The signal will be activated on Monday, November 9th. There will be intermittent lane closures as crews complete final striping and signal configuration. Please use caution as the signal may be in re-flash or dark during certain testing periods.
SUN VALLEY BOULEVARD CORRIDOR IMPROVEMENTS
RTC Project Manager, Jessica Dover, P.E. – (775) 335-1831
Project Information
This project is in the final design phase; construction is anticipatd to start Fall 2027. Sierra Nevada Construction (SNC) will be on site thoruhgout November 2026 to complete subsurface utulity
Work This Week
During the week of November 9-13, work will occur during the day on side streets throughout the project limits.
Traffic Impacts
Drivers and pedestrians should follow posted detours and use caution throughout the work zone. Roadway closures are not anticipated as part of this exploratory work.
TRAFFIC SIGNAL FIBER 26-01 PROJECT
RTC Project Manager, LaShonn Ford, P.E., P.T.O.E – (775) 332-2136
Work This Week
There will be intermittent lane closures on the following radwasy as crews complete paving work:
- 21st Street from Victoria Avenue to Prater Way
- El Rancho Drive from G Street to Wedekind Road
- Sullivan Lane near Greenbrae Drive
VIRGINIA LINE BRT IMPROVEMENTS PROJECT
RTC Project Manager, Kimberly Diegle, P.E. – (775) 335-1844
Work This Week
Construction will be switching to day work, Monday – Friday from 7:00 a.m. – 7:00 p.m. Construction work will only occur at the BRT stations with work resuming along South Virginia between Moana Lane and Hubbard Way next week. The southern Peppermill driveway will be closed in the inbound and outbound directions and traffic will be detoured to the signalized intersection. Travel lanes will be shifted throughout the work zone.
BRT Stations Impacts
- Southbound Station Closures: Mt. Rose, and Orchard Plaza
- Northbound Station Closures: Center Street and Liberty Street
Closed stations are temporarily relocated for passenger pickup. Passengers should follow posted signs to the nearest available stop.
WEST FOURTH STREET SAFTEY (VINE STREET TO MCCARRAN BOULEVARD) PROJECT
RTC Project Manager, Scott Gibson, P.E. – (775) 335-1874
Work This Week
Contractor will complete top lift paving operations on the mainline driveways, and mult-use path. They will then finish concrete work at the roundabouts and other isolated locations in the corridor.
Traffic Impacts
Drivers should expect changing traffic patterns and increased construction activity throughout the corridor. Please slow down, follow posted signs, and use caution when traveling through work zone. Supporting local business in this corridor such as Mi Casa Too, Whispering Vine, and Johnny’s is highly recommended.
- Westbound: One-way traffic from Keystone Avenue to Stoker Avenue (detour at Stoker Avenue to Summit Ridge Drive).
- Eastbound: One-way traffic from McCarran Boulevard to Summit Ridge Drive (ends November 13).
WHITE FIR STREET REHABILITATION PROJECT
RTC Project Manager, Austin McCoy, P.E. – (775) 335-1824
Work This Week
New traffic pattern to begin Tuesday, November 10. Traffic will be shifted on White Fir Street to allow for two-way traffic, with one lane in each direction. Please use caution in the area.